NCDOT Officials Met With Montford Residents

The meeting addressed construction impacts and road closures related to the I-26 Connector Project.

Updated on Sept. 24, 2026 in Openings & Closings

Isometric editorial illustration of a concrete highway overpass bridge spanning a winding riverbed, representing regional transportation infrastructure.
NCDOT representatives and Montford residents reviewed ongoing construction impacts and planned road access changes for the Asheville I-26 Connector project. AI Illustration. Upload story photo >

Live Poll

Do you trust local officials to adequately address resident concerns during major infrastructure projects?

NCDOT officials met with Montford residents on September 23 to discuss ongoing construction impacts. The discussion focused on road closures between the neighborhood and Riverside Drive.

Why it matters

Residents sought clarity regarding noise impacts and the maintenance of access to the French Broad River. This project represents a significant shift in connectivity for local Asheville neighborhoods.

NCDOT has established a timeline that includes a final design noise document in spring 2027 and the reestablishment of river access by winter 2027. A segment of an Asheville street is slated to remain closed through the end of 2027.

The players

NCDOT

The North Carolina Department of Transportation is the state agency responsible for the planning and maintenance of public road networks and infrastructure projects.

Montford

Montford is a historic residential neighborhood in Asheville that is currently navigating the impacts of the I-26 Connector Project.

The details

NCDOT representatives provided project updates and shared research regarding construction-related noise impacts. Attendees expressed concerns about how the I-26 Connector Project affects neighborhood connectivity and river access.

Timeline

  1. September 23, 2026: NCDOT officials met with Montford residents.

  2. Spring 2027: Expected issuance of the final design noise document.

  3. Winter 2027: Scheduled reestablishment of connections to Riverside Drive.

  4. End of 2027: Scheduled reopening of a closed Asheville street.

Market Landscape

This project fits into the broader trajectory of regional infrastructure expansion in North Carolina. It reflects the ongoing state effort to streamline transit corridors despite the competitive pushback from localized urban development concerns.

Residents in the Montford area must adjust to ongoing road closures and noise disruptions through late 2027. Maintaining awareness of these construction milestones is essential for planning daily travel routes and access to the river.

The takeaway

Ongoing communication with state agencies remains the most effective way for residents to track project milestones. Homeowners should prepare for long-term construction logistics until the projected 2027 completion dates.

What happens next

NCDOT is scheduled to issue a final design noise document in spring 2027. Additionally, the department plans to reestablish road connections to Riverside Drive by winter 2027, with a local street reopening by the end of 2027.

Further reading

For more updates on local infrastructure, see Asheville Openings & Closings.

Source note: This article includes information reported by WLOS.

Live Poll

Do you trust local officials to adequately address resident concerns during major infrastructure projects?