Developer Seeks $2.95M TIF for Whole Foods Project
Stratus Properties Inc. has asked Missoula for Tax Increment Financing to fund infrastructure tied to a $29 million Midtown development.
Updated on Nov. 19, 2026 in Business

Live Poll
Should Missoula use public tax money to help fund new commercial developments?
Stratus Properties Inc. is seeking approximately $2.95 million in Tax Increment Financing for a $29 million development on the existing Brooks Street Motor Inn property in Missoula's Midtown neighborhood. The Missoula Redevelopment Agency Board has not yet reviewed the application, which is not yet complete.
Why it matters
The request would fund public infrastructure, including utility upgrades, bicycle and pedestrian facilities, a public plaza and relocation of an open irrigation ditch, rather than the Whole Foods portion itself. Whether the board approves the funding will shape how the project proceeds in Missoula.
The developers seek roughly $2.95 million in TIF financing against a $29 million total project cost, and project 150 permanent jobs and over $250,000 in annual property taxes. The application remains incomplete and unreviewed, and the timing of any board decision has not been set.
The players
Stratus Properties Inc.
Stratus Properties Inc. is a Texas-based real estate development company that has pursued mixed-use projects across the United States.
Missoula Redevelopment Agency
The Missoula Redevelopment Agency is the city body that administers tax increment financing districts and reviews TIF applications within Missoula's urban renewal areas.
The details
The TIF dollars would fund infrastructure sub-projects rather than the Whole Foods portion, which is a tenant ineligible for TIF funds. The developers are also working with Great Burn Brewing on relocating its equipment and facility, and say the project would add a public plaza, infill development and improved safety.
Timeline
Oct. 2: Missoulian first reported on the Whole Foods project.
Oct. 30: Developers' fact sheet was shared by Ward 5 City Councilor Bob Campbell.
Nov. 19: MRA Board met without the Whole Foods project on its agenda.
Early 2027: Abatement and demolition work is expected to begin.
Spring 2028: Building shells could be ready for tenants.
Market Landscape
The request uses Montana's tax increment financing framework, which lets cities direct future property tax growth within urban renewal districts toward infrastructure, to back a private retail and mixed-use redevelopment. Whether Missoula's redevelopment agency approves such a request will signal how the city weighs public infrastructure spending against private commercial investment.
If approved, the project would add a Whole Foods store and about 150 permanent jobs to Midtown Missoula. Residents would see new public plazas, bicycle and pedestrian facilities and infill development, though the store itself would not be funded by the TIF.
The takeaway
Public funding decisions for private retail projects often hinge on whether infrastructure gains reach the wider community. Watching the redevelopment board's review will show how Missoula balances those priorities.
What happens next
The Missoula Redevelopment Agency Board must still review the incomplete TIF application, and abatement and demolition work is expected to begin in early 2027.
Further reading
Track other local business developments in the Openings & Closings section.
Source note: This article includes information reported by The Missoulian.