Missouri Will Close Interstate 70 in Kansas City

A major 11-month closure on Interstate 70 in Kansas City is set to begin on January 11, 2027.

Updated on Oct. 6, 2026 in Openings & Closings

A wide view of a multi-lane highway section featuring orange traffic barrels and concrete construction barriers under a diffuse, overcast sky.
The Missouri Department of Transportation will close Interstate 70 in Kansas City for 11 months starting January 11, 2027, to accelerate major construction repairs. AI Illustration. Upload story photo >

Live Poll

Do you feel prepared for the upcoming 11-month closure of Interstate 70 in your area?

The Missouri Department of Transportation will close Interstate 70 in both directions between Van Brunt and Prospect starting January 11, 2027. This 11-month project is scheduled to remain in effect through December 2027.

Why it matters

Officials opted for a full road closure rather than two years of lane restrictions, aiming to complete the work faster and provide a safer environment for construction crews. The project affects a critical artery that carries 105,000 drivers per day.

The road segment handles 105,000 drivers daily, and the total highway closure is scheduled to span 11 months. Cross streets located above the interstate will remain open for local transit.

The players

Missouri Department of Transportation

This state agency is responsible for the planning, construction, and maintenance of the highway system throughout Missouri.

Gregg/Klice Community Center

This facility serves as a local hub for Kansas City residents and is hosting the public informational meeting regarding the detour.

The details

Through-traffic will be redirected to use Interstate 435, Interstate 470, Interstate 35, and U.S. 71 for the duration of the work. A public meeting is planned at the Gregg/Klice Community Center to discuss detour logistics.

Timeline

  1. January 11, 2027: The Interstate 70 closure begins.

  2. December 2027: The road closure is scheduled to end.

Market Landscape

This project follows the standards set by the Missouri Department of Transportation I-70 improvement project. The full closure approach represents a shift from historical multi-year lane-restriction strategies toward accelerated completion cycles.

Local commuters must prepare for significant traffic rerouting onto Interstate 435, Interstate 470, Interstate 35, and U.S. 71 for nearly a year. Travelers should monitor the official project site for potential updates to the detour plan as the start date nears.

The takeaway

Choosing a total shutdown for road construction generally reduces the overall timeframe compared to partial lane closures. Residents should plan to adjust their daily commutes significantly until the highway reopens in late 2027.

What happens next

A public meeting regarding the specific detour plans will take place from 5 to 7 p.m. at the Gregg/Klice Community Center.

Further reading

For more information on infrastructure projects, visit the Kansas City Openings & Closings section.

More information

For official project details, visit the MoDOT project information page.

Source note: This article includes information reported by Kctv5.