City Pauses Oliver Avenue Flood Project

Minneapolis halted a $5 million Lynnhurst flood mitigation project after vibrations damaged nearby century-old homes and the work exceeded its contract scope.

Updated on Nov. 28, 2026 in Politics

Open excavation trench with steel shoring panels and an orange barricade along a quiet residential street, with a stone retaining wall behind.
Minneapolis halted a $5 million Oliver Avenue South flood mitigation project in Lynnhurst after vibrations damaged nearby century-old homes and work exceeded its contract scope. AI Illustration. Upload story photo >

Live Poll

Do you trust your city to manage neighborhood construction projects without damaging homes?

Minneapolis paused a $5 million flood mitigation project on Oliver Avenue South in the Lynnhurst neighborhood by August 2026 after residents reported damage to homes, trees, sidewalks and a retaining wall. The city and a south Minneapolis construction contractor mutually agreed to terminate the contract.

Why it matters

The city determined the work was exceeding the scope of the contract and could not be completed as originally planned, leaving a stalled piece of a $59 million citywide flood mitigation program. Residents are being asked to document damage and file claims with the city.

The city's $5 million Oliver Avenue project is one piece of a $59 million citywide flood mitigation program, and the extraction does not report total damage costs or claim amounts. Residents have been told to document damage, but the total number of affected properties remains unknown.

The players

City of Minneapolis

The city of Minneapolis is the municipal government that owns and oversees the citywide flood mitigation program and terminated the Oliver Avenue contract.

The details

Construction on the Oliver Avenue project began in 2026 and was scheduled to run through summer 2027 to replace old storm sewer pipes and build a box culvert beneath Oliver Avenue South. Workers encountered sandy soil while digging, and vibrations from shoring work damaged century-old homes near the site, including a 104-year-old house whose owner has lived there 50 years.

Timeline

  1. Construction began in 2026 on the Oliver Avenue project.

  2. The city paused construction in August 2026.

  3. The original scheduled completion was summer 2027.

Big Picture

The Oliver Avenue pause is a setback within the $59 million citywide flood mitigation program, which aims to reduce flooding across south Minneapolis, including the area around Lake Harriet.

Residents near Oliver Avenue South should photograph any damage to homes, trees, sidewalks or retaining walls and file claims with the city. The project's future depends on a pending construction feasibility review.

The takeaway

Homeowners near active city construction should document property conditions before and during work to support any damage claims.

Further reading

Follow more local decisions on the City Hall beat for Minneapolis.

Source note: This article includes information reported by Star Tribune.