Minneapolis Will Close Eastbound I-94 for Repairs

The Minnesota Department of Transportation will close I-94 in Minneapolis for bridge work starting September 25, 2026.

Updated on Sept. 22, 2026 in Car Maintenance

Isometric editorial illustration of a concrete bridge pillar and a section of highway with a single traffic pylon.
The Minnesota Department of Transportation will close eastbound I-94 in Minneapolis between Highway 55 and I-394 for bridge repairs from September 25 to 28, 2026. AI Illustration. Upload story photo >

Live Poll

Is the frequency of highway repairs in your area improving or hindering local travel?

Eastbound I-94 will close between Highway 55 and I-394 beginning at 10 p.m. on September 25, 2026. The highway is scheduled to reopen to traffic at 5 a.m. on September 28, 2026, as part of an ongoing infrastructure project.

Why it matters

The closure is required to facilitate essential bridge repairs over Glenwood Avenue and the Green Line Extension. Completing these structural maintenance tasks is necessary to ensure the long-term safety and stability of the transit corridor.

The closure affects the stretch of I-94 between Highway 55 and I-394. Maintenance crews are performing work on the bridge spanning Glenwood Avenue and the Green Line Extension.

The players

Minnesota Department of Transportation

This is the state agency responsible for the planning, design, and maintenance of Minnesota highway and bridge infrastructure.

The details

Motorists traveling during the closure will be rerouted via Lyndale Avenue to access eastbound I-94. The project is part of a larger maintenance effort that is expected to continue through November 2026.

Timeline

  1. September 24, 2026: Highway 55 ramp to eastbound I-94 closes.

  2. September 25, 2026: Eastbound I-94 closes at 10 p.m.

  3. September 28, 2026: Eastbound I-94 reopens at 5 a.m.

  4. October 10, 2026: Highway 55 ramp closure ends.

  5. November 2026: Project work concludes.

Roadmap

This project reflects a broader industry shift toward prioritizing the rehabilitation of existing bridge infrastructure over new highway expansions. These localized maintenance efforts are critical for aligning aging urban transit corridors with modern safety standards and load-bearing requirements.

Drivers in the area should expect delays and plan for the detour onto Lyndale Avenue while the highway segment remains inaccessible. Commuters are advised to factor extra time into their travel schedules during the active weekend closure period.

The takeaway

Maintaining urban infrastructure requires scheduled disruptions to ensure the continued safety of the regional transportation network. Residents should monitor local traffic alerts regularly for updates regarding the planned weekend closures scheduled through November.

What happens next

Additional weekend directional closures are planned throughout the remainder of the project before it concludes in November 2026.