Paving Wraps Up on Jefferson Avenue Sewer Project

Crews are finishing the east-side lanes of Jefferson Avenue in St. Clair Shores' Nautical Mile after a sewer-road project that began in spring 2025.

Updated on Nov. 19, 2026 in Construction

Wide view of freshly laid asphalt along a suburban boulevard, with a steamroller in the midground and orange barrels along the curb beside brick storefronts.
Crews are finishing paving on the east-side lanes of Jefferson Avenue in St. Clair Shores' Nautical Mile, after a sewer project that began in spring 2025. AI Illustration. Upload story photo >

Live Poll

Do you think big local road projects are worth the disruption to nearby businesses?

Paving crews are finishing the two east-side lanes of Jefferson Avenue in St. Clair Shores' Nautical Mile as part of a sewer-road project. The two west-side lanes between Nine and 10 Mile roads reopened around Labor Day, and businesses in the Nautical Mile have reported a 40% drop in revenue during the work.

Why it matters

The project installs a second sewer pipe along a 1.5-mile stretch of Jefferson Avenue, which officials say increases flow capacity and reduces the need to release partially treated sewage into Lake St. Clair during heavy rains. For St. Clair Shores residents and Nautical Mile merchants, the work has eliminated northern access to the district and blocked the entrance to the Shorepointe nursing and rehabilitation center.

The project's initial $30 million cost has grown to a projected $33 million to $35 million with contingencies, funded by $20 million in federal ARPA money transferred from Macomb County, $5 million in state funds and a $2 million federal earmark. Nautical Mile businesses reported a 40% revenue decline, but the final cost and the full effect on sales remain unconfirmed.

The players

Southeast Macomb Sanitary District

The Southeast Macomb Sanitary District is a regional sewer agency serving member communities including St. Clair Shores, Eastpointe and Roseville, and it oversees the sewer infrastructure that the Jefferson Avenue project is installing.

Macomb County

Macomb County is the Michigan county whose public works department transferred $20 million in federal American Rescue Plan Act funds to support the Jefferson Avenue sewer project.

St. Clair Shores

St. Clair Shores is a city on Michigan's Lake St. Clair shoreline in Macomb County, home to the Nautical Mile business district affected by the Jefferson Avenue construction.

The details

Crews tore up and replaced the west-side lanes to install the sewer pipes deep underground, and officials later decided the east-side lanes should be reconstructed as well. Paving crews are now covering areas in front of business driveways that had been left unpaved for temporary access, taking advantage of 50s to low 60s Fahrenheit temperatures this week.

Timeline

  1. Spring 2025: The Jefferson Avenue sewer-road project began.

  2. Around Labor Day 2026: The two west-side lanes between Nine and 10 Mile roads reopened.

  3. End of 2026: Pavement between Nine and 10 Mile roads is expected to be completed.

  4. 2027: Sewers north of 10 Mile are still being installed, with sidewalks and streetscaping to follow from Nine to 10 Mile roads.

Roadmap

The project draws on American Rescue Plan Act money transferred from Macomb County to pay for underground sewer capacity rather than short-term relief. It follows a pattern in which federal pandemic-era funds are being used for lasting municipal wastewater upgrades along the Lake St. Clair shoreline.

Drivers and visitors heading to the Nautical Mile lose northern access from Jefferson Avenue, and the Shorepointe nursing and rehabilitation center's Jefferson entrance is blocked during the work. Residents and businesses in the area can expect continued lane and driveway disruptions until pavement and sidewalk work wraps up in the coming year.

The takeaway

Local businesses along the Nautical Mile should plan for reduced access and sales disruptions through the end of the project. Residents can reduce detour time by checking construction timing before traveling along Jefferson Avenue.

What happens next

Pavement between Nine and 10 Mile roads is expected to be completed by the end of 2026, with additional sidewalks and streetscaping planned for next year, and sewers north of 10 Mile to Rio Vista-Bon Heur streets to be installed into 2027.

Further reading

For more on local infrastructure work across the area, see Construction coverage for St. Clair Shores.

Source note: This article includes information reported by Macomb Daily.