MDOT to Reconstruct Rochester Road Starting in 2027
The two-year, $40 million project will limit traffic to a single alternating lane between M-59 and Tienken Road.
Updated on Oct. 22, 2026 in Home Renovation

Live Poll
Should local road construction projects be required to maintain two-way traffic to support local businesses?
Beginning in March 2027, the Michigan Department of Transportation will initiate a massive $40 million reconstruction project covering five miles of Rochester Road. The multi-phase effort will restrict traffic to a single lane in alternating directions through 2028.
Why it matters
The project aims to complete critical infrastructure improvements, though local business owners fear the resulting traffic flow limitations will significantly impact their revenue.
The reconstruction covers a five-mile stretch between M-59 and Tienken Road with a total project budget of $40 million. Local business owners anticipate traffic volume reductions ranging from 25 to 50 percent during the construction period.
The players
Michigan Department of Transportation
This state agency is responsible for the design, construction, and maintenance of Michigan's highway and road infrastructure.
The details
The project is divided into two phases, with the first phase spanning from M-59 to the Clinton River Bridge and the second addressing the area from Paint Creek Bridge to Tienken Road. Construction limits travel to a single open lane that alternates between northbound and southbound directions.
Timeline
March 2027: Phase 1 construction begins.
November 2027: Phase 1 construction concludes.
2028: Phase 2 construction occurs throughout the year.
Culture Shift
This project reflects a broader trend of significant infrastructure investment aimed at modernizing aging suburban thoroughfares to handle future capacity needs. It follows the prioritization standards established by the Michigan Department of Transportation's long-range transportation plan.
Residents and commuters should prepare for significant travel delays due to the single-lane, alternating traffic configuration for the next two years. Business owners in the impacted corridor may need to adjust their operations to account for the projected decline in customer accessibility.
The takeaway
Drivers who frequently use this corridor should explore alternate routes well before the March 2027 start date to avoid construction bottlenecks. Businesses along the route may consider increasing their online outreach efforts to maintain customer engagement during the restricted access period.
Further reading
Learn more about local updates in the Home Renovation section.
More information
View the online petition for road traffic plan to see community concerns.
Source note: This article includes information reported by WDIV.