Huron Street Utility Work Starts November 30
Michigan Department of Transportation utility work on downtown Pontiac's Huron Street is scheduled to begin Monday as part of the Woodward Loop rebuild.
Updated on Nov. 26, 2026 in Construction

Live Poll
Do you think downtown road construction usually hurts local businesses in your area?
Utility work on Huron Street in downtown Pontiac is scheduled to begin Monday, November 30, 2026, as part of the Michigan Department of Transportation's effort to rebuild the Woodward Loop. The work will rip out sections of the street and remove road frontage in front of businesses, including The Foundry, a business incubator housing 15 vendors.
Why it matters
Pontiac residents and downtown businesses will face reduced access and disrupted storefronts while the work proceeds. The project is part of a multi-year rebuild of the city's core roadway network that will shape downtown traffic patterns into the next decade.
The Foundry, which houses 15 vendors, saw foot traffic fall by half during the Wayne construction, while sales have increased in the two weeks since that road reopened. How the Huron Street work will affect those figures has not been quantified.
The players
Michigan Department of Transportation
The state agency responsible for maintaining Michigan's highway system, overseeing the rebuild of Pontiac's Woodward Loop.
The Foundry
A business incubator in Pontiac that houses 15 vendors selling products inside the shop.
The details
The utility work will rip out sections of Huron Street, eliminating road frontage where The Foundry's front doors are located. The Foundry plans to use its building's back entrance as a speakeasy-style access point while the work proceeds.
Timeline
Earlier this month: Wayne road reopened, increasing sales at The Foundry.
Monday, November 30, 2026: Huron Street utility work scheduled to begin.
Summer 2027: Huron Street work expected to be completed.
2029: Broader Woodward Loop project scheduled for completion.
Market Landscape
The Huron Street work is one phase of MDOT's Woodward Loop rebuild, a project scheduled for completion in 2029. Its staged timeline means downtown merchants face a multi-year period of altered access rather than a single disruption.
Residents and visitors heading downtown should expect reduced curbside access along Huron Street starting November 30. The city plans to promote downtown Pontiac during construction and post updates online to help people plan trips.
The takeaway
Downtown Pontiac shoppers who plan ahead can keep supporting local storefronts through construction, since businesses like The Foundry are finding ways to maintain access during the work.
What happens next
Huron Street utility work begins Monday, November 30, 2026, and the city plans to post construction updates online.
Further reading
For more on local road projects, see Construction coverage in Pontiac.
Source note: This article includes information reported by WDIV.