Ann Arbor Opens Tunnel Under Amtrak Tracks

The 60-foot tunnel completes a link in the Border-to-Border Trail and ends illegal track crossings on foot.

Updated on Nov. 24, 2026 in City Hall

Concrete tunnel mouth beneath a raised railroad embankment, with a paved trail curving into the opening and young native plantings along its edges.
Washtenaw County opened a 60-foot tunnel beneath Amtrak tracks in Ann Arbor on Nov. 2025, completing a link in the Border-to-Border Trail and ending illegal track crossings on foot. AI Illustration. Upload story photo >

Live Poll

Would you support more local tax money for trails and parks in your area?

Washtenaw County and partners opened a 60-foot tunnel beneath railroad tracks in Ann Arbor for the Border-to-Border Trail, with a ribbon-cutting held in November 2025. Pedestrians and cyclists who had been crossing the Amtrak tracks illegally were given a safe alternative.

Why it matters

The tunnel removes the dead end at the railroad that blocked the trail's continuation, and it addresses liability concerns the railroad raised about pedestrians crossing its tracks. It is a step toward a fully connected trail network for residents of Ann Arbor and surrounding communities.

The tunnel cost about $6 million for engineering and construction, compared with about $1 million for the 0.6-mile trail section built the prior year. The city of Ann Arbor, Washtenaw County Parks, and the Huron Waterloo Pathways Initiative each covered one-third of the cost, and the source does not report any usage data since opening.

The players

Washtenaw County Parks

Washtenaw County Parks is the county parks agency that co-funded the tunnel and the Border-to-Border Trail project.

Amtrak

Amtrak is the national passenger rail operator whose Detroit-to-Chicago trains run on the tracks the tunnel passes beneath.

The details

Crews set 15 concrete sections, each 4 feet long and weighing 55,000 pounds, during a 48-hour rail shutdown in early June 2025. Crews also rerouted a small unnamed creek that previously flowed toward the tunnel site and planted more than 200 native trees, shrubs and grasses.

Timeline

  1. 2002: The tunnel first appeared in a county feasibility study but stalled over funding.

  2. 2019: Feasibility work for the tunnel began.

  3. March 2025: Tunnel construction began.

  4. Early June 2025: Crews set concrete sections during a 48-hour rail shutdown.

  5. November 2025: The tunnel opened with a ribbon-cutting.

Seasonal Patterns

The tunnel extends the 0.6-mile trail section built the prior year, and the project's stated goal is a fully connected trail from Chelsea through Dexter and Ann Arbor to Ypsilanti within the next decade. The source does not compare the project to historical regional trail-building patterns.

Pedestrians and cyclists can now use the tunnel instead of crossing the Amtrak tracks, which was illegal before it opened. The trail continues toward Barton Nature Area and Bandemer Park through the tunnel.

The takeaway

Trail connections often depend on solving a single barrier, and here a tunnel replaced an illegal crossing. Residents who want to follow the trail's progress toward Ypsilanti can check the project's official page.

Further reading

Explore more local coverage in City Hall for context on how Ann Arbor officials handle public infrastructure projects like this one.

More information

Find project details and donation options on the Border-to-Border Trail information and donation page.

Source note: This article includes information reported by Planet Detroit.