ITC Files Oneida-Sabine Lake Transmission Plan

ITC Michigan's construction plan for a 50-mile transmission line now goes before state regulators, with new public sessions set for 2027.

Updated on Nov. 23, 2026 in Utilities

Isometric editorial illustration of steel lattice transmission towers crossing flat farmland under an open sky, evoking a planned regional power line.
ITC Michigan filed a construction plan with state regulators for a 50-mile transmission line running west from Cohoctah Township into Eaton County, with new public sessions set for 2027. AI Illustration. Upload story photo >

Live Poll

Do you support new high-voltage power lines being built through your local area?

ITC Michigan has filed a construction plan with the Michigan Public Service Commission for the Oneida-Sabine Lake Project, a transmission route stretching 50 miles west from Cohoctah Township into Eaton County. The filing includes alternative routes to those proposed so far.

Why it matters

The project is part of a $22 billion midwestern expansion aimed at boosting grid reliability, unlocking cheaper sources of power, and adapting to coal plant closures, growing clean energy development and rising demand. For Michigan residents, the route decisions will shape which properties and communities sit near new high-voltage infrastructure.

The project spans 50 miles, and the Act 30 certificate requirement applies to lines over five miles and 340,000 volts. Which of the alternative routes will be selected remains unresolved.

The players

ITC Michigan

ITC Michigan is the Michigan operating subsidiary of ITC Holdings, an electric transmission company that builds and maintains high-voltage power lines across the state.

Michigan Public Service Commission

The Michigan Public Service Commission is the state regulatory body that reviews utility construction filings and decides on Act 30 certificates of public convenience and necessity for major transmission lines.

The details

ITC Michigan evaluated possible route segments through more than 14 meetings, collecting 2,500 pieces of feedback from roughly 2,000 attendees. Following Michigan Public Service Commission guidelines, the utility is mailing invitations to anyone within a mile of the route, between routes, or on the routes, and a survey will remain open after the sessions.

Timeline

  1. November 2026: ITC Michigan filed its construction plan with the Michigan Public Service Commission.

  2. January 2027: New public information sessions begin.

  3. Mid-2027: ITC Michigan plans to file its Act 30 application with the Commission.

  4. 2030: Construction is slated to begin.

  5. 2032: Construction is slated to wrap up.

Roadmap

The Oneida-Sabine Lake filing follows the certificate process set by Michigan's Act 30 of 1995, which requires state review of transmission lines over five miles and 340,000 volts. It is one segment of a $22 billion midwestern expansion that utilities are advancing to replace retiring coal capacity and meet rising demand.

Residents within a mile of the proposed corridors in Livingston, Ingham and Eaton counties may receive invitations to the sessions and can weigh in on route options. Property owners near the final route could see transmission infrastructure affecting their land.

The takeaway

Public feedback has already shaped the route options under review, and the upcoming 2027 sessions give residents another chance to influence which corridor is ultimately approved.

What happens next

ITC Michigan will hold new public information sessions beginning in January 2027, and plans to file its Act 30 application with the Michigan Public Service Commission in mid-2027.

Further reading

For context on how regional grid investments are being planned, explore more Utilities coverage.

Source note: This article includes information reported by WHMI 93.5 FM.