Energy Secretary Extends Campbell Coal Plant Order
The seventh federal emergency order keeps Michigan's J.H. Campbell coal plant running through February 12, 2027.
Updated on Nov. 14, 2026 in Utilities

Live Poll
Should the federal government keep aging coal plants open to protect grid reliability?
U.S. Secretary of Energy Chris Wright issued the seventh emergency order keeping the J.H. Campbell coal plant in Port Sheldon Township, Ottawa County, open. The order takes effect Sunday and continues through February 12, 2027.
Why it matters
The plant was originally set to close in May 2025, and it has stayed open for more than a year through a series of federal emergency orders. For Michigan residents, the continued operation keeps a major coal plant in service amid ongoing legal and cost debates.
Consumers Energy reported $295 million in costs tied to the plant from May 2025 through June 2026, the period since the original closure date passed. The seventh order extends operations, but the source does not break down how those costs will be allocated going forward.
The players
Chris Wright
Chris Wright is the U.S. Secretary of Energy, who has issued the series of emergency orders keeping the plant open.
Dana Nessel
Dana Nessel is the Michigan Attorney General, who has challenged the previous federal renewal order.
Consumers Energy
Consumers Energy is a Michigan-based utility that reported the plant's costs over the past year.
U.S. Department of Energy
The U.S. Department of Energy is the federal agency that issues and renews the emergency orders keeping the plant running.
The details
The Department of Energy keeps the plant running through successive federal emergency orders, each renewed before the prior one expires. Michigan Attorney General Dana Nessel has challenged the previous renewal order, which expires Saturday, and the Department of Energy cites critical grid reliability issues in the Midwest as its reason.
Timeline
May 2025: The J.H. Campbell plant was originally scheduled to close.
August 14, 2026: The previous renewal order was issued.
November 14, 2026: The seventh emergency order was issued.
November 15, 2026: The seventh emergency order takes effect.
February 12, 2027: The seventh order expires.
Market Landscape
The repeated use of federal emergency powers to keep a retiring coal plant running extends a pattern in which the Department of Energy overrides planned utility retirements. This places the Campbell plant among the central test cases for how far federal emergency authority can reach into state-regulated power generation.
Michigan ratepayers are the ones paying for the plant's continued operation, with Consumers Energy reporting $295 million in costs since May 2025. The extension means those costs continue to accrue through at least February 12, 2027, so customers should watch future rate filings for how they are passed along.
The takeaway
Federal emergency orders are now the primary tool keeping aging coal capacity online, and their cost and legal consequences will fall on Michigan utility customers. Tracking the February 2027 expiration and any court ruling on the challenge will show whether this pattern continues.
What happens next
The seventh emergency order expires February 12, 2027, and the previous order's expiration on Saturday will determine whether the legal challenge proceeds.