Four Lakes Dams Near Completion, Edenville Lags
Work continues at Secord and Edenville dams while Sanford and Smallwood have reached legal lake levels.
Updated on Nov. 4, 2026 in Current Conditions

Live Poll
Do you support the Four Lakes dam restoration project despite its ongoing costs?
The Four Lakes Task Force reported that Sanford and Smallwood dams have reached legal lake levels, with Smallwood completing final adjustments and cleanup. Work remains at Secord and Edenville dams, where Secord is projected to reach substantial completion in November.
Why it matters
The projects are restoring lake levels and shoreline across the Four Lakes region after the 2020 dam failures. Completion timelines and refill dates affect residents, property owners and recreation users in Michigan who depend on these lakes.
Sanford had no ongoing construction and Smallwood is finishing gate, seal and grading work, with most punch-list items expected to be completed in October. The task force has not yet reconciled project costs, remaining contingency funds and grant funding.
The players
Four Lakes Task Force
The Four Lakes Task Force is the state-established body overseeing reconstruction of the dams and lakes in the Midland County region following the 2020 failures.
The details
Crews are completing final adjustments and cleanup at Smallwood, including gate and seal work, grading and site restoration. A Secord gate was returned to its manufacturer for repairs, which the manufacturer is paying for, though the task force has incurred engineering costs tied to the repair.
Timeline
Oct. 7: Task Force webinar outlined work stages at each dam.
October: Most Smallwood punch-list work expected to be completed.
November: Substantial completion projected at Secord.
Spring 2027: Secord lake expected to begin refilling.
September 2027: Substantial completion projected at Edenville.
Seasonal Patterns
The rebuilding follows the May 2020 Edenville and Sanford dam failures that drained the Four Lakes in mid-Michigan. Current progress reports track how the restoration timelines compare with the original recovery schedule set after those failures.
Residents and property owners near Smallwood and Sanford can expect lake levels to be at legal height now, while Secord and Edenville lakeshore areas remain under construction. Lakeshore users should plan around construction zones and refill dates before Secord's spring 2027 refill and Edenville's September 2027 completion.
The takeaway
The Four Lakes restoration is moving through its final phases, with Smallwood and Sanford already at legal levels and Secord and Edenville still on schedule for 2027. Readers tracking the lakes should watch the spring 2027 Secord refill as the next visible milestone.
What happens next
Secord substantial completion is projected for November, with lake refill expected in spring 2027, and Edenville substantial completion is projected for September 2027.