Montgomery County Reopens Woodmont Avenue in Bethesda
The roadway between Wisconsin Avenue and Leland/Strathmore Streets reopened after a closure tied to a WSSC Water valve vault project.
Updated on Nov. 27, 2026 in City Hall

Montgomery County reopened a portion of Woodmont Avenue in Bethesda to traffic on November 26, 2026, after the stretch between Wisconsin Avenue and Leland/Strathmore Streets had been closed to through traffic since July 20. The reopening came more than three weeks after the originally anticipated November 2 date, weather permitting.
Why it matters
The closure, part of WSSC Water's Leland Avenue 54-inch Large Valve Vault Replacement Project, rerouted drivers for more than four months. Reopening restores a key downtown connection for commuters and visitors ahead of the Thanksgiving holiday.
The stretch was closed to through traffic for more than four months, and reopening came more than three weeks after the originally anticipated date. Local business deliveries and access for residents of The Solair and Prenuvo Bethesda were maintained throughout the closure.
The players
WSSC Water
The Washington Suburban Sanitary Commission, the regional utility that operates water and sewer infrastructure in Montgomery and Prince George's counties.
Montgomery County
The county government that oversees roadway management and reopened Woodmont Avenue to traffic.
The details
Through traffic was directed to alternate routes while crews worked on the stretch. The roadway now runs again between Wisconsin Avenue and Leland/Strathmore Streets in Bethesda.
Timeline
July 20: Closure of the stretch to through traffic began.
November 2: Originally anticipated reopening date, weather permitting.
November 26, 2026: Woodmont Avenue reopened to traffic.
Thanksgiving holiday: Reopening timed to restore the downtown connection.
City Hall
The reopening closes out a closure driven by WSSC Water's Leland Avenue 54-inch Large Valve Vault Replacement Project, a utility upgrade that required Montgomery County to restrict one of Bethesda's downtown corridors for months. The county's decision to tie the reopening to the Thanksgiving holiday reflects its focus on restoring downtown access during a high-traffic period.
Drivers can once again use Woodmont Avenue between Wisconsin Avenue and Leland/Strathmore Streets rather than detouring to alternate routes. Business deliveries and residential and retail access along the corridor were maintained throughout the closure.
The takeaway
Commuters and downtown visitors can resume using the direct Woodmont Avenue route through Bethesda heading into the holiday period. Checking traffic updates before travel can help avoid any residual lane adjustments as work wraps up.