Board Approves $6.6M Charlotte Hall Water Treatment Update

The Maryland Board of Public Works signed off on the veterans home project, awarded to a Lancaster, Pa., contractor.

Updated on Nov. 24, 2026 in Politics

Board Approves $6.6M Charlotte Hall Water Treatment Update

The Maryland Board of Public Works approved a $6,628,937 water treatment update for Charlotte Hall Veterans Home at its Nov. 18 meeting in Annapolis. Maryland Environmental Services awarded the contract to HRI/M2 Construction of Lancaster, Pa.

Why it matters

The existing treatment building has deteriorated from long-term exposure to high humidity, and many of its components have exceeded their useful lives. The work is intended to bring the facility into compliance and reduce pathogens in water serving residents of the state-run veterans home.

The $6,628,937 award carries a 450-day term and a spending cap of $1,974,000 through the end of the current fiscal year, with $4,654,937 still awaiting Board authorization. Remaining spending timelines beyond that cap are not addressed in the source extraction.

The players

Maryland Board of Public Works

The state panel of the governor, comptroller and treasurer that must approve major state contracts and spending.

Maryland Environmental Services

A state agency that manages environmental and infrastructure projects for Maryland government facilities.

HRI/M2 Construction

A construction firm based in Lancaster, Pa., awarded the Charlotte Hall water treatment contract.

The details

Bidding opened in August through Maryland Environmental Services, and the contract went to HRI/M2 Construction. The project includes rehabilitation of the existing elevated water storage tank, which was constructed in 1982 and holds 250,000 gallons. A 2025 Water Quality Report by the agency found copper and lead each tested in the 90th percentile.

Timeline

  1. August: Bidding for the project opened through Maryland Environmental Services.

  2. Nov. 18: The Board of Public Works approved the project in Annapolis.

  3. End of current fiscal year: The $1,974,000 spending cap applies before further authorization.

  4. February 2028: Scheduled completion of the water treatment work.

Legacy Systems

The Board's staged authorization, with a fiscal-year spending cap and a further tranche awaiting approval, follows the standard process by which Maryland funds long-term facility rehabilitation. The 1982 storage tank and aging treatment building illustrate how state-run facilities built decades ago now require large, multi-year capital repairs.

Residents of Charlotte Hall Veterans Home will see the water treatment system upgraded over a 450-day schedule ending in February 2028. The work is meant to address pathogen levels and deteriorating treatment components that affect the drinking water supply.

The takeaway

Large state infrastructure projects are often approved in stages, so the full cost of a facility upgrade may not be fixed at the first vote. Watching for later Board authorizations is the best way to track how such projects proceed.

What happens next

Maryland Environmental Services will return to the Board of Public Works to request authorization of the remaining $4,654,937 for the project.