Landowners Ask Supreme Court to Block Maryland Power Line
Property owners in three Maryland counties say PSEG should not be allowed onto their land for the 67-mile MPRP transmission project.
Updated on Nov. 20, 2026 in Law

Live Poll
Should utilities be allowed to build new power lines across private land?
Landowners in Carroll, Frederick and Baltimore Counties have petitioned the U.S. Supreme Court to deny Public Service Enterprise Group (PSEG) access to their property for the Maryland Piedmont Reliability Project, a 67-mile transmission line. The Fourth Circuit Court of Appeals previously upheld a preliminary injunction granting PSEG field survey access to private properties in August.
Why it matters
The dispute pits landowners' property rights against a utility's claim that the line is needed to avert an approaching power crisis, and it remains unresolved while the state has not approved the project's certificate. The outcome could shape how far utilities can go in surveying private land before final approvals are granted in Maryland.
The Maryland Piedmont Reliability Project spans 67 miles, and the Fourth Circuit upheld a preliminary injunction in August allowing surveys to proceed. It remains unknown whether the Supreme Court will accept the landowners' petition, and the Maryland Public Service Commission has not yet approved the project's state certificate.
The players
Public Service Enterprise Group (PSEG)
PSEG is a publicly traded New Jersey-based utility holding company that is the developer seeking to build the Maryland Piedmont Reliability Project.
Pacific Legal Foundation
The Pacific Legal Foundation is a nonprofit public interest law firm that represents property owners in litigation over government and regulatory actions.
The details
Landowners represented at no cost by Aaron Newell of the Pacific Legal Foundation have asked the Supreme Court to deny PSEG access to their properties in Carroll, Frederick and Baltimore Counties. During survey periods hunting is not allowed on the affected land, and PSEG states the line is needed to prevent an approaching power crisis.
Timeline
August: The Fourth Circuit Court of Appeals upheld PSEG's preliminary injunction for field surveys.
January: PSEG is expected to file its response to the landowners' petition.
February: The Supreme Court is expected to take up the case.
Mid-2027: The Maryland Public Service Commission is expected to decide on the state certificate.
Legal Context
The case follows the Fourth Circuit's August decision upholding a preliminary injunction that let PSEG survey private land before final litigation concluded. The landowners' petition now asks the Supreme Court to reconsider whether such access should be granted while the state certificate remains pending.
Property owners in Carroll, Frederick and Baltimore Counties may face PSEG surveyors on their land while the litigation continues. Until the Supreme Court and the Maryland Public Service Commission act, the scope of access rights remains uncertain for affected landowners.
The takeaway
The case highlights how preliminary court orders can allow utilities onto private land before final state approval, a question landowners across Maryland may watch closely. Readers following the dispute should track both the Supreme Court docket and the Public Service Commission's decision on the state certificate.
What happens next
PSEG is expected to file its response to the Supreme Court petition in January, and the Supreme Court is expected to decide whether to take up the case in February.
Further reading
For related court and legal developments, see Maryland Law coverage.
Source note: This article includes information reported by WYPR.
Live Poll
Should utilities be allowed to build new power lines across private land?