MassDOT Replaces Armory Street Bridges Through 2032
The Massachusetts Department of Transportation is rebuilding two 1934 bridges over rail lines in Springfield in phases.
Updated on Nov. 24, 2026 in Industry

Live Poll
Do you think the Armory Street bridge detours are worth the disruption?
The Massachusetts Department of Transportation is replacing back-to-back Armory Street bridges in Springfield, which were built in 1934 over two rail lines, with work running through 2032. Northbound traffic is detoured onto Taylor, Chestnut, and Liberty Streets during construction.
Why it matters
The bridges have reached the end of their life after nearly a century, with rusted girders and visible rebar in deteriorating concrete. The project also addresses tight turns onto Albany Street that the existing design requires, for residents and drivers across Springfield.
The bridges date to 1934 and the first phase is estimated to finish in January 2027, while the second phase, expected to take three times as long, is projected to conclude in 2032. Cost details and a finalized second-phase traffic plan have not been announced.
The players
Massachusetts Department of Transportation
The state agency responsible for transportation infrastructure, including highways and bridges across Massachusetts, and the lead agency overseeing this bridge replacement.
The details
The first phase works on the west side of the bridge while a single southbound lane stays open. Trucks are diverted from St. James Avenue to Bay and Tapley Streets, and the project will add a turn lane onto Albany Street and replace sidewalks with a multi-purpose corridor on each side of Armory Street.
Timeline
1934: Armory Street bridges built over two rail lines.
January 2027: First phase on the west side estimated to be completed.
Summer 2028: Second phase expected to begin.
2032: Second phase expected to be finished.
Construction Landscape
Replacing 1934-era bridges over active and abandoned rail lines reflects the wider challenge of Massachusetts maintaining infrastructure built before 1950. The phased, detoured approach used on Armory Street mirrors how the state manages long-running structural replacements while keeping traffic moving.
Northbound drivers will be detoured onto Taylor, Chestnut, and Liberty Streets, and truck traffic is being diverted from St. James Avenue to Bay and Tapley Streets during construction. A single southbound lane remains open on Armory Street during the first phase, so commuters should expect slower travel through the corridor.
The takeaway
Drivers and residents near Armory Street should plan for detours and reduced lanes through at least 2032, as the project is staged over several years. Checking the state's route notices before traveling through the area can help avoid delays.
What happens next
The first phase of the west-side work is estimated to finish in January 2027, and the second phase is expected to begin in summer 2028.
Further reading
Explore more on Construction projects shaping the region around Springfield.
Source note: This article includes information reported by The Reminder.