MassDOT Maps Costs to Close Mass Central Rail Trail Gaps
A conceptual state planning study prices three missing segments of the proposed 104-mile Boston-to-Northampton greenway.
Updated on Nov. 27, 2026 in Industry

Live Poll
Should the state spend $170 million on a bridge for a rail trail?
MassDOT has published a conceptual planning study on closing three gaps in the proposed 104-mile Mass Central Rail Trail, which runs from Boston to Northampton. Estimated costs range from $13.1 million for the Hardwick segment to about $170 million for a bridge spanning the Nashua River gorge in Clinton.
Why it matters
Roughly 72 miles of the trail are already open, so the remaining gaps determine whether a continuous off-street route across Massachusetts becomes possible. The study frames the cost of each gap against projected visitor and economic benefits for communities along the corridor.
The study prices the Hardwick gap at $13.1 million, the Springfield-to-Franklin Street segment at $16.7 million, and the Clinton gorge bridge alternative at about $170 million, with the Swift River crossing estimated at $92 million including land acquisition. Whether those costs will be covered has not been determined.
The players
Massachusetts Department of Transportation (MassDOT)
The state agency that oversees transportation planning and infrastructure across Massachusetts, including multi-use trail corridors.
East Quabbin Land Trust
A regional land conservation organization that has already built several trail segments in Hardwick along the former rail corridor.
The details
The Hardwick gap would use a new separated shared-use path along State Route 32 plus new sidewalks on River Run, while the Clinton option would span the Nashua River gorge with a 1,000-foot bridge that avoids an at-grade crossing of Boylston Street. The Belchertown-to-Palmer gap, 4.9 miles long, is the least complicated, with the Town of Belchertown owning most of the existing path and securing MassTrails grant funding to begin rehabilitating the Jabish Brook bridge.
Timeline
December 2020: The Town of Clinton purchased its section of the corridor from the Boston & Maine Railroad.
2021: MassDOT commissioned a high-level feasibility study of the full corridor.
June 2022: The Clinton trust received a MassTrails grant for tunnel remediation design.
2023: Analysis projected the completed network could generate more than $200 million annually.
2031: A separately funded 1.2-mile Maple Street trail extension is slated for construction.
Transportation Corridor Context
The Mass Central Rail Trail follows the former Boston & Maine Railroad right-of-way, and the study extends the conversion of that corridor into the remaining gaps that suburban development has blocked. The Hardwick detour route illustrates how the abandoned line has been swallowed by later construction.
Residents near the Belchertown-to-Palmer and Hardwick gaps could see the lowest-cost connections first, since those segments are the least expensive to build. Trail users in the region would gain a continuous off-street route once any of the remaining gaps is closed.
The takeaway
Closing the remaining trail gaps depends on funding decisions that the conceptual study does not yet resolve. Watch for which segments receive construction money first, since the lowest-cost gaps are the most likely to advance.
Further reading
For more on planned infrastructure across the state, see Transportation coverage on Wisevoter.
Source note: This article includes information reported by Hoodline.