Court Upholds Shreveport Data Center Permit
The Second Circuit Court of Appeal ruled against plaintiffs in the final appeal of their lawsuit over the West Shreveport AWS data center.
Updated on Nov. 18, 2026 in Data Centers

Live Poll
Do you think large data centers are good for communities where they're built?
The Second Circuit Court of Appeal ruled in favor of the City of Shreveport, rejecting the final appeal of a lawsuit over a data center permit. Plaintiffs Tyler Gordon, Mary Blakemore, and Michael Craft had challenged the City Council's decision.
Why it matters
The ruling clears a path for STACK Infrastructure's large data center project on the Resilient Technology Park site in west Shreveport. The court found that nondisclosure agreements alone did not warrant reversing the City Council's decision.
STACK Infrastructure is constructing three data centers of roughly 1.3 million square feet each, at a cost of about $6 billion per facility. The source does not specify power draw or cooling capacity for the campus.
The players
STACK Infrastructure
A data center developer building three large campuses on the Resilient Technology Park site in west Shreveport.
City of Shreveport
The municipal government whose City Council approved the Special Use Permit and was defended in the appeal.
The details
Judge Ramone Lafitte dismissed the plaintiffs' legal action on April 20, and the Second Circuit Court of Appeal later responded to the claims point by point. The City of Shreveport's permits for buildings one and two and a driveway at the Resilient Technology Park site have been filed, and E.E. REED East Coast was chosen as general contractor.
Timeline
Dec. 3: Metropolitan Planning Commission voted 4-3 opposing the permit.
Dec. 18: Shreveport City Council unanimously overturned the commission's decision.
April 20: District Judge Lafitte dismissed the plaintiffs' legal action.
Nov. 18, 2026: Second Circuit Court of Appeal ruled against the plaintiffs.
Market Landscape
Data center projects are spreading across Caddo Parish, Bossier Parish, Blanchard, and Benton, with the Shreveport site joining several others in the Ark-La-Tex region. The court's dismissal of nondisclosure-based challenges sets a precedent for similar large-scale developments in the area.
The project is expected to hire between 540 and 750 permanent employees across the three data centers, creating local job opportunities. Residents may see changes in utility infrastructure, as the source notes a $100 million AEP Transmission Control Center construction project by SWEPCO.
The takeaway
Court rulings on local permit challenges can set the pace for large infrastructure projects, and residents tracking similar developments should watch how cities handle public disclosure concerns during the approval process.
What happens next
STACK Infrastructure aims to bring its first buildings online in middle to late 2027, with full campuses expected to be complete in 2029.
Further reading
Explore more on Data Centers in the Shreveport area.
Source note: This article includes information reported by The Shreveport-Bossier City Advocate.
Live Poll
Do you think large data centers are good for communities where they're built?






