Entergy Waterford 5 Gas Plant Cost Rises to $1.8B
Entergy Louisiana reports a 63 percent cost increase for the St. Charles Parish plant as it prepares to seek approval for seven more gas plants.
Updated on Nov. 24, 2026 in Utilities

Live Poll
Should data centers pay the full cost of the power plants they need?
Entergy Louisiana reported to the Public Service Commission that the Waterford 5 gas plant in St. Charles Parish is now projected to cost $1.8 billion, $676 million more than the original $1.1 billion estimate. The filing, submitted November 12, also details a $4.4 billion total cost for the Hyperion project, up from $4 billion.
Why it matters
The cost growth raises questions for Louisiana ratepayers and regulators as Entergy prepares to seek approval for seven new gas plants and related transmission lines. Meta would pay the final costs of the gas plants through minimum bill payments under its contract with Entergy Louisiana, while the Sierra Club has urged regulators to deny the proposal.
The Waterford 5 cost increase of $676 million, or 63 percent, is attributed to unique geotechnical conditions at the site and rising labor and equipment costs. Much of the underlying cost detail remains redacted in the public version of the filing.
The players
Entergy Louisiana
Entergy Louisiana is the state's regulated electric utility, serving residential and commercial customers and operating the generation and transmission assets at issue in the filing.
Public Service Commission
The Louisiana Public Service Commission is the state regulatory body that reviews utility cost filings and decides whether proposed power plants and transmission lines are approved.
Meta
Meta is the technology company whose Hyperion data center in Richland Parish is the driver of the new generation capacity, and which has a minimum bill contract with Entergy Louisiana.
Sierra Club
The Sierra Club is a national environmental organization that has urged regulators to reject Entergy's proposal for new gas plants.
The details
Entergy's filing says the Waterford 5 site required construction above grade on 120-foot piles because of weak soil. Entergy had also acquired 41 of 320 right-of-ways, about 13 percent, for the Mount Olive-to-Sarepta 500-kilovolt transmission line.
Timeline
- Summer 2024: The original Waterford 5 cost estimate was prepared.
- May 2026: Entergy filed documents showing the above-grade piling requirements.
- November 12, 2026: Entergy filed updated cost documents with the Public Service Commission.
- November 19, 2026: The Sierra Club criticized the project and called for a denial vote.
- December 2026: Entergy plans to seek approval for seven new gas plants.
Market Landscape
The Commission's review of Entergy's filings is shaping how Louisiana pays for large data center demand, with Meta's minimum bill contract determining who absorbs the cost of new gas capacity. Entergy's cost overrun on Waterford 5 will be weighed against the remaining seven-plant request as the Commission considers how much new generation the state needs.
Because Meta's minimum bill payments are designed to cover the final cost of the new gas plants, the rising estimates may affect what Louisiana utility bills ultimately reflect if the Commission approves the proposal. Residents can follow the Commission's review, where the cost details will be debated.
The takeaway
Large infrastructure cost estimates can grow substantially between planning and construction, and the Commission's review of redacted filings will determine how much of that risk reaches customers. Readers should watch how the seven-plant proposal is evaluated once it reaches the Commission.
What happens next
Entergy plans to seek Public Service Commission approval for seven new gas plants and related transmission lines next month, which will open a new round of public review and comment.
Further reading
For more on how the state's power sector is planned and priced, see Utilities coverage across Louisiana.
Source note: This article includes information reported by Hanna Newspapers.