Venture Global Plans 5 GW Louisiana Data Centers

The company targets data-center compute capacity at two Cameron and Plaquemines parish sites by 2031.

Updated on Nov. 11, 2026 in Data Centers

Wide view of a flat Louisiana marsh site with steel power modules, cable trays, and louvered data-center halls under an overcast sky.
Venture Global plans two Louisiana data-center campuses in Cameron and Plaquemines parishes targeting 5 gigawatts of compute capacity by 2031. AI Illustration. Upload story photo >

Live Poll

Do you expect your local electricity bills to rise because of new data centers?

Venture Global plans to build data-center compute capacity at two Louisiana sites in Cameron and Plaquemines parishes, targeting 5 gigawatts by 2031. The company outlined the plans on November 10, 2026, pairing the facilities with power infrastructure designed to operate off the public grid.

Why it matters

The plan would add substantial compute capacity in Louisiana while relying on self-supplied power rather than the public grid. Capacity additions are tied to commitments from investment-grade customers, so the pace of the buildout depends on those commitments materializing.

Venture Global targets 5 gigawatts of data-center compute capacity by 2031, starting with 250 megawatts online in late 2028 and a potential 10 gigawatts by the end of 2034. The October framework allows for up to 16 power-island units rated at 720 megawatts each, though it is a staged arrangement rather than a completed order.

The players

Venture Global

Venture Global is a U.S. energy infrastructure company that operates liquefied natural gas facilities in Louisiana and is now pursuing data-center development alongside its power-supply plans.

The details

Venture Global outlined data-center compute plans for two sites in Cameron and Plaquemines parishes on November 10, 2026. The sites are paired with power infrastructure designed to operate without relying on the public grid, supported by the equipment framework the company announced in October covering power-island units, transformer equipment, and grid equipment.

Timeline

  1. October 2026: Venture Global announced a framework for expanding its power-network equipment.

  2. November 10, 2026: The company outlined its data-center compute plans.

  3. Year-end 2026: Venture Global plans to order its first power plant.

  4. Early 2027: The company plans to order a second power plant.

  5. Late 2028: Venture Global targets bringing 250 megawatts of compute capacity online.

Roadmap

Venture Global's plan follows a growing pattern of data-center developers building self-supplied power rather than waiting on public-grid interconnection. The Louisiana sites apply that model to a gas-rich region already home to the company's energy infrastructure.

For Louisiana residents, the plan signals new large-scale industrial development in Cameron and Plaquemines parishes, though its direct effect on local jobs, utility rates, and land use is not detailed in the available information. Because the sites are designed to run off the public grid, the near-term impact on household electricity supply is expected to be limited.

The takeaway

Watch the year-end 2026 and early 2027 power-plant orders, since they will show whether the 5-gigawatt target is moving from framework to construction. Customer commitments will also determine how quickly capacity comes online.

What happens next

Venture Global plans to order its first power plant by year-end 2026 and a second early in 2027, with the first 250 megawatts of compute targeted online in late 2028.

Further reading

For broader context on how these facilities are being built, explore more coverage in Data Centers.