University Closes Woodland Avenue for Utility Work
Woodland Avenue is closed just south of Euclid Avenue from 9 a.m. to 3 p.m. daily through Dec. 4 for utility work tied to the Woodland Village project.
Updated on Nov. 27, 2026 in Industry

The University of Kentucky closed Woodland Avenue just south of Euclid Avenue starting Nov. 23, with crews connecting sanitary and water lines for the Woodland Village construction project. Traffic is detoured toward Rose Lane and Rose Street during the daily closure hours.
Why it matters
The closures and lane shifts affect drivers, cyclists and parking users moving through the University of Kentucky campus in Lexington. Route changes on South Upper Street and the KTRDC parking lot closure will persist for weeks, requiring commuters to plan alternate routes and parking.
Woodland Avenue closes daily from 9 a.m. to 3 p.m. through Dec. 4, while the KTRDC parking lot closure is expected to continue through approximately mid-February. The South Upper Street traffic pattern is expected to remain in place for about two months, and the schedule for further changes has not been detailed.
The players
University of Kentucky
The University of Kentucky is a public research university in Lexington, Kentucky, and the largest institution of higher education in the state.
The details
Crews are connecting sanitary and water lines for the Woodland Village construction project during the Woodland Avenue closure. Beginning Nov. 25, traffic on South Upper Street was shifted west around a Central Heating Plant boiler project construction area, eliminating the southbound bicycle lane and making several on-street parking spaces unavailable.
Timeline
Nov. 23: Woodland Avenue and KTRDC parking lot closures began.
Nov. 25: South Upper Street lane shift began.
Nov. 28: Woodland Avenue will be open all day for the UK-Louisville football game.
Dec. 4: Woodland Avenue closure is scheduled to end.
Mid- to late December: University Drive section between Complex and Hospital drives is expected to reopen.
Market Landscape
The Woodland Village project and the Central Heating Plant boiler project are part of the University of Kentucky's ongoing campus infrastructure upgrades in Lexington. These closures reflect the university's continued investment in utility systems that serve its south campus buildings.
Drivers heading to the University of Kentucky campus should expect Woodland Avenue detours during daytime hours through Dec. 4. Commuters using South Upper Street or the KTRDC parking lot will face reduced bike lanes, fewer parking spaces and lane shifts for about two months.
The takeaway
Plan for detours and reduced parking on the University of Kentucky campus through mid-February, and check the closure schedule before driving to south campus. Allow extra time for travel near Woodland Avenue and South Upper Street during the work period.
What happens next
Woodland Avenue is scheduled to reopen after Dec. 4, and University Drive between Complex and Hospital drives is expected to reopen in mid- to late December.