The Pennyrile Regional Energy Agency, a public agency based in Todd County, is building a 53-mile natural gas pipeline funded by a $30 million state appropriation. Spending records for October 2025 through September 2026 show payments to engineering, legal, lobbying and consulting firms, and the agency has sued landowners to secure remaining easements.
Why it matters
The agency's spending and its legislative exemption from Kentucky Public Service Commission oversight raise questions about how public money is being used on a large infrastructure project. Kentucky residents along the proposed route in several counties are directly affected by the easement disputes.
The agency's records show $373,750 and $548,900 in engineering fees, $287,599.39 in legal fees and $55,256 in lobbying fees over twelve months, leaving about $21.8 million on hand. The total cost of the 53-mile, 16-inch pipeline and whether that spending will be recouped from future gas customers has not been reported.
The players
Pennyrile Regional Energy Agency
A public agency in Western Kentucky based in Todd County that is building a 53-mile natural gas pipeline and is the subject of the spending and litigation reported here.
Rep. Jason Petrie
A Kentucky state representative whose legislation exempted the agency from Public Service Commission regulation during the 2026 session.
The details
The agency selected D2 Energy and McGhee Engineering, and McGhee was the only firm to respond to a 2022 request for qualifications. The agency stated it hired consultant Tim Thomas, a former co-chairman of the Appalachian Regional Commission, for his political connections, and retained a Frankfort firm to monitor legislation affecting the project. Rep. Jason Petrie passed a state law exempting the agency from Public Service Commission regulation.
Timeline
2019: The Todd County Natural Gas District was formed by Guthrie and Trenton officials.
2021: The agency rebranded and proposed the regional pipeline project.
2022: The Kentucky legislature appropriated $30 million to the agency.
2026 legislative session: Petrie's law exempting the agency from Public Service Commission oversight passed.
Industry Context
Under Kentucky's regulatory framework, the Public Service Commission ordinarily oversees utility projects, so the Petrie law marks a departure from that standard. The exemption places a multimillion-dollar public pipeline outside that commission's review.
Kentucky residents in the pipeline's route counties, including Lyon, Trigg, Caldwell and Christian, may face continued easement litigation affecting their land. Ratepayers may eventually bear the cost of the agency's spending if it is recovered through gas rates.
The takeaway
Public infrastructure projects funded by appropriations can carry costs and oversight questions that reach beyond the project itself. Readers tracking utility spending should watch how the agency's exemption and its litigation develop.
Further reading
For more on the regulation of gas infrastructure, see Utilities coverage across the state.
Source note: This article includes information reported by The Times Leader.
Live Poll
Do you trust local government to spend public money fairly on infrastructure projects?