Developer Pulls First Permit for Meridian Project

The Overland Park Development Company secured the first building permit for the nearly $2 billion Meridian development at 103rd and Antioch.

Updated on Nov. 12, 2026 in Construction

Wide photograph of a cleared, graded development lot on flat open land under a pale sky, with a single parked excavator and a bare concrete foundation pad.
The Overland Park Development Company pulled the first building permit for the nearly $2 billion Meridian project at 103rd and Antioch after the city pushed its first construction milestone to July 2027. AI Illustration. Upload story photo >

Live Poll

Do you trust Overland Park to hold developers to their construction deadlines?

The Overland Park Development Company picked up the first building permit for the Meridian development, a nearly $2 billion project at 103rd and Antioch. The city amended the development agreement over the summer, moving the first construction milestone from July 2026 to July 2027.

Why it matters

The amended timeline gives the project another year before its first construction milestone, shaping when Overland Park residents can expect new mixed-use development at one of the city's major sites. The permit marks a concrete step after the site has seen no vertical construction so far.

The first building is a 317-unit mixed-use structure, with the developer expecting a 27-month construction schedule. The last project milestone is set for 2038, though the report does not detail the phasing between now and then.

The players

Overland Park Development Company

The developer leading the Meridian project, which has been working on the site since the city's first action in 2019.

The details

The developer returned to the city's Economic Development Committee in October to report on behind-the-scenes work ahead of groundbreaking. The company expects construction on the first building to begin in November.

Timeline

  1. 2019: Overland Park took its first action on the project.

  2. July 2026: Original deadline for the first construction milestone.

  3. July 2027: Amended deadline for the first construction milestone.

  4. October 2026: Developer reported to the Economic Development Committee.

  5. November 2026: Expected groundbreaking on the first building.

Construction Pipeline

The Meridian project's amended development agreement sets its first construction milestone for July 2027, a one-year extension from the original July 2026 deadline. The project's first building is now on track to break ground in November after the permit was issued.

Residents near 103rd and Antioch should expect construction activity to begin in November as the first 317-unit building starts. The amended schedule means the full mixed-use development will take longer to deliver than originally planned.

The takeaway

Large mixed-use projects often move through permits and amended agreements well before visible construction begins, so the timeline shifts reported here are worth tracking. The Meridian project's first groundbreaking now sits in November, with the first milestone pushed to 2027.

What happens next

Groundbreaking on the first building is expected in November, and the first construction milestone is due by July 2027.

Further reading

For more on local building activity, see Construction coverage in Overland Park.

Source note: This article includes information reported by KSHB 41 Kansas City News.