Olathe Approves $567K for Santa Fe Rebuild

The city council voted 7-0 to fund additional engineering work tied to the roughly $200 million I-35 and Santa Fe project.

Updated on Nov. 11, 2026 in Lifestyle

Photograph of a half-built concrete highway overpass with exposed rebar and retaining walls beside an empty roadway under flat, overcast daylight.
The Olathe City Council voted 7-0 to approve $567,375 in additional engineering work from HNTB for the roughly $200 million I-35 and Santa Fe interchange project. AI Illustration. Upload story photo >

Live Poll

Would you support major highway construction even if it closes your usual routes for years?

The Olathe City Council voted 7-0 on November 3 to approve $567,375 in additional engineering work by Kansas City-based firm HNTB. The work covers design for bridges, retaining walls, drainage and traffic planning during construction, and was already part of the total project budget.

Why it matters

The project is intended to address congestion and safety along one of Olathe's busiest corridors. Residents who drive the I-35 and Santa Fe interchange should expect the most significant local traffic effects once the city's portion reaches its final phase.

The council approved $567,375 in added design work within a roughly $200 million project, with Olathe's share funded by $40 million in general obligation bonds. Closures include a three-month closure of the southbound Old 56 off-ramp and a six-month closure of the Old Highway 56 bridge.

The players

Olathe City Council

The elected governing body of Olathe, Kansas, which voted 7-0 to approve the additional engineering contract and oversees the city's portion of the Santa Fe rebuild.

Kansas Department of Transportation

The Kansas state agency responsible for state highways, which manages the I-35 portion of the project including new auxiliary lanes.

HNTB

A Kansas City-based engineering and infrastructure firm awarded the $567,375 in additional design work for the project.

The details

The engineering agreement with HNTB covers design of bridges, retaining walls and drainage, plus planning for how traffic can keep moving during construction. The Kansas Department of Transportation manages the I-35 portion, which will replace the existing interchange with a single-point urban interchange and widen the Old Highway 56 bridge for two new auxiliary lanes, while Olathe oversees work along Santa Fe where crews are relocating utilities.

Timeline

  1. November 3, 2026: Olathe City Council approves $567,375 in engineering work.

  2. Late 2026 or early 2027: KDOT is set to begin adding auxiliary lanes between Santa Fe and 119th Street.

  3. Late 2027: Santa Fe corridor rebuild is scheduled to begin.

  4. 2029: Final phase of the city's portion, when Santa Fe is expected to close completely.

  5. Summer 2030: Roughly $200 million project is estimated to wrap up.

Health Landscape

The project extends the Kansas Department of Transportation's I-35 corridor expansion through Johnson County by pairing highway auxiliary lanes with a city-led rebuild of the Santa Fe interchange. Its design approach, which replaces the existing interchange with a single-point urban interchange, reflects a model of coordinating state and municipal work on the same congested corridor.

Drivers who use the I-35 and Santa Fe interchange should prepare for lane additions and utility work that will affect traffic before the corridor rebuild is complete. The most disruptive phase for local commuters is expected in 2029, when the city's portion reaches its final stage and Santa Fe closes completely.

The takeaway

Large infrastructure projects like this one proceed in stages, so commuters should expect a series of closures and phased construction over several years rather than a single disruption. Monitoring KDOT and city announcements will help drivers plan routes ahead of each phase.

What happens next

KDOT is set to begin adding auxiliary lanes between Santa Fe and 119th Street in late 2026 or early 2027, with construction on the highway portion possibly starting as soon as this winter. The Santa Fe corridor rebuild is scheduled to begin in late 2027.

Further reading

For more on local construction and infrastructure projects, see Home Renovation coverage for Olathe.

Source note: This article includes information reported by Johnson County Post.