KDOT Advances U.S. 83 Expressway Reconstruction
Kansas Department of Transportation crews are reconstructing U.S. Highway 83 and installing a fiber-optic system along the corridor.
Updated on Nov. 2, 2026 in Construction

Live Poll
Do you think driving conditions in your area are getting better?
The Kansas Department of Transportation reported progress on a reconstruction project replacing and rerouting U.S. Highway 83 into a two-lane expressway with passing lanes. Crews are also installing a fiber-optic system for the Advanced Technology Project along the route.
Why it matters
The project improves safety by consolidating access points, improving intersection angles, and adding turn lanes and lighting. It also prepares U.S. 83 for possible future expansion to a four-lane highway for Kansas drivers.
The reconstruction runs from about 2.5 miles north of the Haskell/Finney County line to Garden City at the Arkansas River, while the fiber-optic system will extend the KanDrive billboard and camera network across 131 miles of the corridor. The report does not disclose project cost or contract value.
The players
Kansas Department of Transportation
The state agency responsible for planning, building, and maintaining Kansas's highway network, including the U.S. 83 reconstruction and Advanced Technology Project.
The details
Crews are replacing and rerouting the existing alignment, consolidating highway access points, and improving intersection angles on the route. Work on the Advanced Technology Project, which involves installing a fiber-optic system, has been underway since 2023.
Timeline
2023: Crews began work on the Advanced Technology Project.
End of 2026: Construction and testing of the fiber-optic system are scheduled to finish.
October 2027: This phase of the highway reconstruction is expected to be completed.
Through 2028: Performance monitoring of the technology system is scheduled to continue.
Construction Outlook
The U.S. 83 project follows the Kansas practice of pairing highway reconstruction with the KanDrive electronic billboard and camera system, extending that network to 131 miles of the corridor. It also positions the route for eventual four-lane expansion, a step that would build on the current two-lane expressway design.
Drivers on U.S. 83 will encounter consolidated access points, new turn lanes, and added lighting as the expressway takes shape. The fiber-optic work will also bring KanDrive electronic billboards and cameras to 131 miles of the corridor.
The takeaway
Reconstruction and technology upgrades on U.S. 83 are being built together, so drivers should expect both roadway changes and new roadside systems over the next two years. Planning routes around the schedule milestones through 2027 can help reduce delays.
What happens next
The highway reconstruction phase is expected to be completed in October 2027, and fiber-optic construction and testing are scheduled to finish by the end of 2026.
Further reading
Explore more Kansas Construction coverage for context on state highway projects.
Source note: This article includes information reported by KSN-TV.