Gary Will Begin Genesis Convention Center Demolition
The city moves to clear derelict structures to make room for new housing and community space.
Updated on Oct. 14, 2026 in Construction

Live Poll
Do you believe demolition of blighted buildings improves your community's long-term outlook?
Gary will begin the demolition of the Genesis Convention Center on October 16, 2026. This project aims to address safety hazards and taxpayer burdens while preparing the site for future residential development.
Why it matters
The center cost taxpayers $8 million in operational shortfalls over five years, and stabilization would exceed $10 million. Removing the structure is intended to clear land for much-needed housing and local business growth.
The city plans to add 150 residential units at 5th and Broadway alongside 90 units at 504 Broadway. The project follows a $10 million estimate for repairs that would have been required to stabilize the Genesis Convention Center.
The players
Powers and Sons Construction
This construction firm provided the assessment estimating repair and stabilization costs for the Genesis Convention Center.
University of Notre Dame School of Architecture
This academic institution is collaborating with the city to guide redevelopment efforts.
The details
City officials finalized engineering surveys and environmental assessments to prepare for the removal of the Genesis center and other aging buildings like the City Methodist Church and St. Mary's Mercy Hospital. The demolition process will prioritize exterior work before structural removal and site restoration in collaboration with the University of Notre Dame School of Architecture.
Timeline
Exterior demolition of the Genesis Convention Center begins on October 16, 2026.
Structural demolition of the Gordon's complex begins in late October 2026.
The on-site parking garage demolition starts in early November 2026.
The city expects complete demolition and site restoration by August 24, 2027.
Market Landscape
This move reflects a broader trend of clearing abandoned, high-liability structures to stimulate urban density. It positions Gary to transition from maintaining aging assets to creating new revenue-generating residential infrastructure.
Residents should anticipate localized traffic disruptions during the scheduled demolition phases over the coming months. The project aims to improve neighborhood safety and increase housing availability, potentially impacting local residential supply and property conditions.
The takeaway
The city is actively clearing derelict properties to reduce long-term financial liabilities and create space for new housing. Residents can monitor the official city portal for specific street closure updates throughout the construction timeline.
What happens next
Exterior demolition begins October 16, 2026, followed by the Gordon's complex in late October 2026, the parking garage in early November 2026, and full site restoration by August 24, 2027.
Further reading
For more information on current infrastructure projects, visit the Gary Construction section.
Source note: This article includes information reported by Chicago Tribune.