Council Approves $9.8M Contract for Vann Family Crossing
The 1,000-foot pedestrian bridge over Coliseum Boulevard will connect 130 miles of local trails once complete.
Updated on Nov. 25, 2026 in Industry

Fort Wayne City Council unanimously approved a $9.8 million construction contract for the Vann Family Crossing, a 1,000-foot pedestrian bridge, and renamed the Pufferbelly Trail Pedestrian Bridge to honor the Vann family. The contract was awarded to Beaty Construction, a Boggstown-based company, after bids came in above expected cost.
Why it matters
Total project cost has risen to $12.3 million, well above the initial $7 million estimate, leaving a $2.3 million shortfall that officials said could have jeopardized the project. Funding from a Vann Family Foundation donation, city, county and other partners helped close the gap for a bridge that will link Fort Wayne's trail network.
The $12.3 million total project cost sits well above the original $7 million estimate, with a $2.3 million shortfall filled by donations and public funds. Officials have targeted roughly $400,000 in savings with the contractor, and the final cost reduction has not yet been confirmed.
The players
Fort Wayne City Council
The elected legislative body of Indiana's second-largest city, which approves city contracts, naming decisions and budget appropriations.
Beaty Construction
A Boggstown-based construction firm that won the contract to build the Vann Family Crossing after the lowest and most responsible bid was selected.
The details
The city council approved the naming and construction contract unanimously, and the contract went to the lowest and most responsible of three bids. Funding sources include $5 million from the Vann Family Foundation, more than $4 million from the city, $1.4 million in tax increment financing, $1 million from the Allen County Capital Improvement Board, $500,000 from Allen County commissioners and $50,000 from Steel Dynamics.
Timeline
Thanksgiving: Funding issue needed resolution before the construction bid expired.
September: Ritchie told the capital improvement board about the funding deadline.
January 2027: Construction on the bridge is expected to begin.
Summer 2028: Bridge construction is expected to be completed.
Construction Cost Pressure
The bridge's price rise from $7 million to $12.3 million reflects the higher construction costs that have pushed many municipal infrastructure projects beyond their original budgets. Fort Wayne's approval within Indiana's 90-day bid window shows the city moving quickly to avoid losing the contractor's price.
Pedestrians and cyclists in Fort Wayne will gain a direct route across Coliseum Boulevard once the bridge opens in 2028. Funding from city taxpayers and tax increment financing helped close a $2.3 million gap that could otherwise have stalled the project.
The takeaway
Large public projects often face cost growth between initial estimates and final bids, and securing private donations alongside public funds can keep them on track. Residents interested in the bridge's progress can watch for updates as construction begins next year.
What happens next
Construction on the Vann Family Crossing is expected to begin in January 2027, with completion targeted for summer 2028.