Utilities Board Approves $855K for Winston Thomas Project

The Bloomington Utilities Service Board added funds to two contracts for a new service and maintenance center on the former Winston Thomas plant site.

Updated on Nov. 17, 2026 in Utilities

Utilities Board Approves $855K for Winston Thomas Project

The Bloomington Utilities Service Board voted Monday, November 16, 2026, to add $855,352 to two contracts for the Winston Thomas service and maintenance center project. Most of the increase will go toward design work on the South Walnut Street site.

Why it matters

The added funds cover higher costs after a 2½-year delay and additional work needed to complete the plans. The project would move utilities staff out of a facility at 600 E. Miller Drive that the department had outgrown, consolidating administrative and maintenance staff in one location for Bloomington residents.

The board approved an $855,352 combined increase, with $785,409 added to the design contract and $69,943 to the construction manager contract. The total city spending on the project has not been calculated, and the board did not receive that figure.

The players

Bloomington Utilities Service Board

The appointed board that oversees the city's utilities department and approves its major contracts and capital projects.

The details

A covered walkway will connect the service center and the maintenance center, and architects will revise landscaping and rearrange offices within the existing building footprint. The Winston Thomas site was previously home to a city wastewater treatment plant built in 1935, which closed in 1983 when the Dillman Road plant opened; PCBs from local factories were found on the property in 1975, and the city said the federal Superfund cleanup was complete in 2022.

Timeline

  1. 1935: The city built a wastewater treatment plant at the Winston Thomas site.

  2. 1975: PCBs were found at the property, prompting a federal Superfund cleanup.

  3. 1983: The Winston Thomas plant closed when the Dillman Road plant opened.

  4. 2022: The city said the cleanup was complete and the EPA allowed unrestricted redevelopment.

  5. November 16, 2026: The Utilities Service Board approved the added contract funds.

Industry Context

The project reuses a site first developed as a city wastewater plant in 1935 and later cleared through a federal Superfund cleanup that began after PCB contamination was found in 1975. The city's decision to build a new service center there follows the EPA's 2022 allowance of unrestricted redevelopment.

The project will consolidate Bloomington utilities staff and equipment into one site, which could affect how quickly the department responds to service issues for residents. Current utility customers will not see a direct rate change from this contract increase, according to the figures provided.

The takeaway

Large public infrastructure projects often grow in cost after delays, so tracking contract amendments can show how public money is being spent over time. Residents interested in city spending can request the full project budget from the Utilities Service Board.