Northwestern Breaks Ground on $275M Cancer Addition

The Orland Park expansion, funded in part by a $225 million St. George Foundation donation, is set to open to the public in late 2029.

Updated on Nov. 18, 2026 in Cancer

Wide view of a half-built concrete office building and partially framed parking garage with a yellow crane over a graded construction lot under overcast sky.
Northwestern Medicine broke ground on a $275 million cancer addition in Orland Park on November 18, funded in part by a $225 million gift from the St. George Foundation. AI Illustration. Upload story photo >

Live Poll

Do you trust local hospitals to deliver good cancer care?

Construction has begun on a $275 million cancer addition to Northwestern Medicine's Orland Park campus, with groundbreaking on November 18, 2026. The St. George Foundation donated $225 million toward the project, which includes a four-story office building and a 484-car parking garage.

Why it matters

The expansion adds to the existing Orland Park cancer center, which will gain infusion stations, diagnostic imaging, and radiation treatment capacity for local patients. Officials say the facility's cyclotron technology is expected to reduce patient wait times and speed up treatment delivery for residents of Orland Park and surrounding communities.

The $275 million project is funded primarily by a $225 million donation from the St. George Foundation, with a planned 484-car garage and four-story office building. Construction will employ 350 temporary workers, while 150 permanent staff are expected once the cancer institute opens.

The players

Northwestern Medicine

Northwestern Medicine is an integrated academic health system based in Chicago that operates hospitals and outpatient facilities across the Chicago area.

St. George Foundation

The St. George Foundation is a philanthropic organization that funded the $225 million donation supporting the Orland Park cancer addition.

Orland Park Village Board

The Orland Park Village Board is the elected governing body of the village of Orland Park, Illinois, responsible for zoning and land-use approvals.

The details

The Orland Park Village Board approved the project three months before groundbreaking, allowing the building to sit 30 feet from existing wetlands instead of 50 feet, raising the maximum height to 51.5 feet, and removing a landscape buffer requirement along the east side of the lot. The project is planned for 15300 West Ave.

Timeline

  1. Three months before groundbreaking: Orland Park Village Board approved the $275 million addition.

  2. November 18, 2026: Construction broke ground on the St. George Cancer Institute facility.

  3. Through the winter: Construction is scheduled to continue.

  4. Late 2029: Officials aim to open the building to the public.

Health Landscape

The addition extends the existing Orland Park cancer center, adding infusion, diagnostic imaging, and radiation capacity to a campus that already serves the south suburbs. It reflects a pattern of large suburban hospital systems expanding oncology services closer to where patients live rather than relying only on downtown Chicago centers.

Patients in Orland Park and nearby communities may gain access to infusion, imaging, and radiation treatment closer to home once the building opens in late 2029. The cyclotron technology is expected to shorten wait times for treatments.

The takeaway

Larger suburban cancer centers are bringing treatment closer to home, so patients in the south suburbs may find fewer trips to the city are needed as the Orland Park campus expands.

Further reading

For more on local cancer care options, explore Cancer coverage on Wisevoter.