Naperville to Complete Road Construction Phase in November
The first phase of water main replacement work near Ogden Avenue and Washington Street concludes November 13.
Updated on Oct. 15, 2026 in Construction

Live Poll
Is infrastructure maintenance in your area keeping pace with the needs of the community?
Naperville will complete the first phase of its road construction and water main project on November 13, 2026. This initial stage involves work around the Ogden Avenue and Washington Street intersection that began earlier this year.
Why it matters
The city is replacing water infrastructure originally installed between the 1950s and 1960s to maintain reliability. The second phase, initially intended to follow sooner, was postponed to 2027 due to pending permit approvals.
The current infrastructure initiative consists of 2 total construction phases. This project replaces aging water mains, valves, hydrants, and service lines throughout the area.
The players
Illinois Department of Transportation
This state agency manages the permitting process for road-related infrastructure projects.
Naperville North High School
This educational institution serves as a geographic boundary marker for the project's second phase.
The details
Crews are actively updating water mains dating back to the 1950s and 1960s, a process that requires lane closures and shifting traffic patterns. The upcoming work affects Ogden Avenue between Washington Street and Wright Street, as well as Washington Street between Ogden Avenue and Bauer Road.
Timeline
Construction initially began in spring 2025.
The project restarted in May 2026.
The first phase is scheduled for completion on November 13, 2026.
The second phase is slated to begin in 2027.
Market Landscape
Public infrastructure projects often face delays due to the Illinois Department of Transportation permitting requirements. These regulatory hurdles frequently dictate the pace of city-level capital improvements and inter-agency coordination.
Residents and commuters should anticipate changing traffic patterns and lane closures near the Ogden Avenue and Washington Street intersection through November 13. Future travel plans should account for the upcoming second phase of construction scheduled for 2027.
The takeaway
Maintaining aging water infrastructure is essential for long-term utility reliability in growing cities. Residents can check the city website periodically for updates on 2027 road closures and specific start dates for the project's final phase.
What happens next
The city will begin the second construction phase in 2027, which will extend the water main west to Mill Street and reach the area near Naperville North High School.
Further reading
For more information on ongoing infrastructure upgrades, visit Naperville Construction.
Source note: This article includes information reported by NCTV17.