Mount Prospect Approves $1.33M Rand Road Lighting
Trustees accepted a low bid for pole installation and approved an engineering contract for Algonquin Road improvements.
Updated on Nov. 24, 2026 in City Hall

Live Poll
Do you support your village spending more on road lighting and sidewalks?
Mount Prospect trustees voted to spend $1.33 million installing street lighting along Rand Road, accepting the low bid of Hydro-Exc. Inc. of Griffith, Indiana. Trustees also approved an engineering contract for lighting and sidewalk improvements along Algonquin Road.
Why it matters
The Rand Road bid came in about 14% above estimates, with higher drilling costs cited as the main driver. Algonquin Road currently has street lighting only around the Algonquin Road-Busse Road-Dempster Street intersection, so the project addresses a gap for village residents and motorists.
The Rand Road project will install about 57 poles, each 40 feet tall, along a one-mile stretch, while $424,900 is authorized for construction engineering on Algonquin Road, where $339,920 of that amount comes from federal funding. Trustees did not address how the 14% bid overage will be covered.
The players
Hydro-Exc. Inc.
A contractor based in Griffith, Indiana, whose low bid was accepted for the Rand Road street lighting installation.
Christopher B. Burke Engineering, Ltd.
An engineering consulting firm awarded up to $424,900 in construction engineering services for the Algonquin Road project.
The details
Trustees accepted the low bid from Hydro-Exc. Inc. for the Rand Road lighting, which drilling costs pushed above estimates. For Algonquin Road, trustees approved a contract with Christopher B. Burke Engineering, Ltd. covering a sidewalk and a shared-use path, with about half the roadway already having sidewalks on both sides.
Timeline
Last week (relative to November 23, 2026): Trustees voted on the Rand Road lighting and Algonquin Road engineering contracts.
2027: The Village Resource Center is scheduled to open on Algonquin Road.
End of 2027: Both the lighting and road projects are expected to be largely complete.
Civic Context
Illinois sets roadway lighting standards through its transportation department, and the Rand Road and Algonquin Road projects follow those requirements as the village extends illumination along major corridors. The extraction does not detail the specific standards applied.
Residents along Rand Road and Algonquin Road can expect new lighting and sidewalk work through 2027, with construction affecting nearby traffic. The village has not specified detour or lane-closure details in the extraction.
The takeaway
Village infrastructure decisions often reshape daily travel safety long before construction finishes, so residents who drive or walk these corridors should watch for schedule updates from village trustees as the 2027 completion dates approach.
Further reading
Follow local decisions on the City Hall coverage for more on Mount Prospect trustee votes.
Source note: This article includes information reported by Chicago Tribune.