Developer Secures Financing for Evanston Tower
A 29-story, 419-unit apartment tower at 605 Davis St. moves toward construction after financing was secured.
Updated on Nov. 17, 2026 in Construction

Live Poll
Do you think new apartment towers in your area will make housing more affordable?
A developer has secured financing to begin construction of a 29-story, 419-unit apartment tower at 605 Davis St. in Evanston. The city approved foundation permits last week, and building permits for the tower are under review.
Why it matters
When completed, the 298-foot tower will be the tallest building in Evanston, adding substantial apartment supply to the city. About 84 of the units, or 20%, are expected to be offered as affordable.
A construction loan of about $113 million from CIBC and ULLICO covers roughly 65% of the project's total cost, with equity secured through a joint venture with Kayne Anderson. Building permits remain under review, and the full project cost was not disclosed.
The players
CIBC
CIBC is a major Canadian bank with lending operations in the United States, and it provided part of the construction loan for the project.
ULLICO
ULLICO is an insurance and investment company that provided part of the construction loan for the 605 Davis St. tower.
Kayne Anderson
Kayne Anderson is an investment firm that secured equity for the project through a joint venture partnership.
The details
Site preparation at 605 Davis St. included utility work and the September demolition of a former bank drive-thru. Foundation permits approved by the city allow work on the foundation and structural core of the first four stories while building permits are reviewed.
Timeline
September: Former bank drive-thru at the site was demolished.
Last week: The city approved foundation permits for the project.
November 17, 2026: Financing for construction was announced.
Market Landscape
The 605 Davis St. project will qualify for the Cook County Affordable Housing Special Assessment Program, which provides a substantial property tax reduction for developments that include affordable units. Its 20% affordable share is positioned to take advantage of that incentive as the tower advances through permitting.
The added apartment supply could affect rental options in Evanston once the tower is complete. The 84 affordable units are expected to give some residents access to lower-cost housing in a new building.
The takeaway
Large residential projects often depend on layered financing and phased permitting, so watching the building permit decision is the clearest signal of when work on the full tower will advance.
What happens next
Building permits for the 605 Davis St. tower are under review, and the city's decision on those permits will determine when full construction can proceed.