Amtrak Starts Chicago Union Station Platform Conversion

The project converts a former mail platform into a high-level platform for passengers with mobility devices, luggage and strollers.

Updated on Nov. 27, 2026 in Transportation

Isometric editorial illustration of a raised concrete platform beside parallel steel tracks, with a sloped ramp rising to its level.
Amtrak is raising a 1,500-foot former mail platform at Chicago Union Station into a level passenger platform, funded by a $49.6 million federal grant and local matching funds. AI Illustration. Upload story photo >

Live Poll

Do you think transit in your area is getting better for riders?

Amtrak is converting a roughly 1,500-foot former mail platform at Chicago Union Station into a raised passenger platform under the Chicago Hub Improvement Program. The project is funded by a $49.6 million federal grant, $40 million in federal appropriations and a $22.4 million local match from Amtrak, the city of Chicago and Cook County.

Why it matters

The conversion is intended to make boarding easier and faster for riders using mobility devices, luggage and strollers at one of the busiest stations in the region. Because Superliner railcars cannot use the high-level platform, the project also ties into Amtrak's February push to move toward single-level trainsets across its network.

The project is backed by $49.6 million in Federal Railroad Administration grant funding, $40 million in federal appropriations and a $22.4 million local match pooled by Amtrak, Chicago and Cook County. The platform stands 4 feet above ground and runs roughly 1,500 feet, while construction is expected to take about 30 months.

The players

Amtrak

The National Railroad Passenger Corporation is the federally chartered company that operates intercity passenger rail service across the United States, including the Chicago Union Station platform project.

The details

The raised platform sits between the two through tracks on the east side of Union Station and will be reached by the existing crossover. Passengers will roll up an incline onto the platform, which will include a climate-controlled waiting area with restrooms.

Timeline

  1. February: Amtrak announced it is seeking single-level trainsets across the board.

  2. Early November: Amtrak announced the start of construction.

  3. End of this year: Construction is expected to begin.

  4. 2029: The platform project could finish at the earliest.

  5. Early 2030s: Amtrak expects to replace its long-distance railcars.

Roadmap

The platform conversion is being delivered under the Chicago Hub Improvement Program, which is advancing rail capacity and access work at Union Station. It also fits into Amtrak's broader effort to adopt single-level railcars that can use high-level platforms across its network.

Riders using mobility devices, luggage or strollers will be able to board from a raised, climate-controlled platform once the project is complete, instead of at ground level. The change is also designed to speed up boarding for all passengers at Chicago Union Station.

The takeaway

Trains that serve Chicago Union Station will increasingly depend on single-level equipment, so riders should expect boarding changes as the platforms are converted. Passengers with mobility needs can plan around the raised platform once construction is finished.

What happens next

Construction is expected to begin toward the end of this year and take about 30 months, with completion in 2029 at the earliest. Amtrak also plans to replace its long-distance railcars by the early 2030s.

Further reading

For more on regional rail infrastructure, see Transportation coverage of major station and rail projects.

Source note: This article includes information reported by Chronicle Media.