Perpetua Advances Stibnite Gold Project in Idaho

Early construction is underway at the abandoned Stibnite mine site as the company pursues a tungsten funding framework.

Updated on Nov. 26, 2026 in Industry

Wide photograph of a graded construction pad and new power poles on a forested mountain slope in central Idaho under soft morning light.
Perpetua Resources advanced early construction at its Stibnite gold project in Idaho and announced a nonbinding memorandum of understanding with an unnamed aerospace and defense company contemplating up to $55.5 million in tungsten funding. AI Illustration. Upload story photo >

Live Poll

Should the US expand domestic mining for critical minerals like antimony and tungsten?

Perpetua Resources Corp has advanced early construction on its Stibnite gold project in central Idaho, after the US Forest Service approved the mine plan in January 2025. The company also announced a nonbinding memorandum of understanding with an unnamed major US aerospace and defense company that contemplates up to $55.5 million in nonequity tungsten funding.

Why it matters

The project would redevelop an abandoned Idaho mine into a source of gold, silver and antimony, and the antimony reserve is described as the only identified one in the United States. The tungsten arrangements and a US Army award point to defense-related demand for the metals the site could supply.

Perpetua reports unrestricted cash of $443.4 million at September 30, 2026, against a $2.58 billion project capital expenditure. The company's projections for gold output and antimony supply have not yet been tested by operations, and the nonbinding tungsten funding remains unconfirmed.

The players

Perpetua Resources Corp

Perpetua Resources Corp is a publicly traded mining company developing the Stibnite gold, silver and antimony project in central Idaho.

The details

Perpetua is redeveloping the abandoned Stibnite mine site for gold, silver and antimony, with worker-housing civil works completed in late August 2026 and power-pole installation starting in October 2026. The US Army awarded up to $40 million through the Defense Ordnance Technology Consortium for a 36-month tungsten evaluation program, and Perpetua will match that contribution.

Timeline

  1. January 2025: US Forest Service approved the Stibnite mine plan.

  2. October 2025: Early construction work started after permits were secured.

  3. May 21, 2026: Export-Import Bank board approved a $2.9 billion loan.

  4. October 26, 2026: US Army awarded up to $40 million for tungsten evaluation.

  5. November 17, 2026: Nonbinding tungsten memorandum of understanding announced.

Market Landscape

The Stibnite project follows the 2025 US Forest Service approval of the mine plan on a long-abandoned site, and its antimony reserve is positioned against the country's reliance on imported antimony. Its tungsten funding talks place Perpetua alongside defense-linked demand for critical minerals.

For Idaho residents, the project is expected to create about 950 direct construction jobs and 550 operations jobs. Those employment figures are projections that depend on financing closing and construction proceeding on schedule.

The takeaway

The Stibnite project shows how a permitted, long-idle mine site can be redeveloped for minerals tied to defense supply chains, but its gold, antimony and tungsten plans still depend on financing and partner commitments not yet finalized.

What happens next

Closing of the US Export-Import Bank financing is expected in the first quarter of 2027.

Further reading

For related coverage, see Manufacturing in the Idaho business news section.

Source note: This article includes information reported by Mining Weekly.