Idaho Lab Completes Hot Cell Research Facility

Battelle Energy Alliance finished the 52,211-square-foot building at the Idaho National Laboratory complex, the first new hot cell facility built at the DOE complex in nearly 50 years.

Updated on Nov. 18, 2026 in Science

Plain concrete research building with a long flat metal roof on open sagebrush desert in Idaho, with distant buttes under a clear sky.
Battelle Energy Alliance completed a 52,211-square-foot hot cell research facility at Idaho National Laboratory, the first new DOE hot cell built in nearly 50 years. AI Illustration. Upload story photo >

Battelle Energy Alliance has completed a 52,211-square-foot hot cell research facility at the U.S. Department of Energy's Idaho National Laboratory complex. It is the first new hot cell facility built at the DOE complex in nearly 50 years and the largest project undertaken by the DOE Office of Nuclear Energy.

Why it matters

The facility gives researchers shielded space to handle radioactive materials for nuclear energy work at a site that has not added this type of capability in decades. Its completion marks the end of a major construction effort for the DOE Office of Nuclear Energy.

The building includes four shielded hot cells with 4-ft-thick concrete walls and more than 100 feedthroughs and penetrations, plus three instrument enclosures built from 8.5-in.-thick steel. The stub does not state when research operations will begin in the facility.

The players

Battelle Energy Alliance

Battelle Energy Alliance is the contractor that manages and operates the Idaho National Laboratory for the U.S. Department of Energy.

U.S. Department of Energy

The U.S. Department of Energy is the federal agency that oversees the national laboratory system, including the Idaho National Laboratory complex.

Idaho National Laboratory

Idaho National Laboratory is a U.S. Department of Energy research facility in Idaho focused on nuclear energy and related science.

The details

Crews embedded 16,000-lb door frames into the 4-ft-thick concrete walls and faced delayed steel deliveries that complicated installation of the shielded enclosure walls. Long-lead components arrived after the building envelope was closed, so teams used temporary roof openings to position equipment and complete concrete placements.

Timeline

  1. Completion of the 52,211-square-foot facility was announced by Battelle Energy Alliance; the exact completion date is not specified in the source.

Big Picture

The completion follows nearly 50 years without a new hot cell at the Idaho complex, the last such build before this project. It positions the site to expand shielded research capacity for the DOE Office of Nuclear Energy's programs.

For researchers and staff working with nuclear materials, the facility adds shielded laboratory space and offices at the Idaho complex. Readers who follow federal energy research spending can track how the new capacity is used as operations begin.

The takeaway

Large federal research buildings like this one take years to finish because specialized shielding, delayed components and tight clearances all add complexity. Watching completion milestones can show how far a publicly funded lab project has moved from design to operation.