Sioux City Council Weighs $292.3M Wastewater Contract

The council is asked Monday to award PKG Contracting the first phase of the wastewater treatment plant rebuild.

Updated on Nov. 22, 2026 in Politics

Isometric editorial illustration of two round concrete treatment tanks and stainless steel pipes on flat prairie ground, evoking municipal wastewater infrastructure.
Sioux City Council will be asked Monday to award PKG Contracting a $292.3 million contract to rebuild its wastewater treatment plant after terminating its deal with Kiewit. AI Illustration. Upload story photo >

Live Poll

Do you trust Sioux City to deliver the wastewater plant rebuild on budget?

Sioux City Council will be asked Monday to award a $292.3 million contract to PKG Contracting, Inc. of Fargo, North Dakota, which submitted the lowest bid of $292,376,900 for the first phase of the wastewater treatment plant rebuild. The vote follows the council's decision to terminate its contract with Kiewit Infrastructure Co. on Aug. 3.

Why it matters

The rebuild is required to meet sizing and specifications set by the Iowa Department of Natural Resources, which sued the city in 2022 over alleged repeated environmental violations at the plant. The project must be completed by Dec. 31, 2031, and is funded in part by a sewer rate increase approved by the council in 2023.

The lowest of three bids came in roughly 10% under the city's $325 million estimate, while the council rejected Kiewit's guaranteed maximum price of $467,115,659.28 two weeks before terminating that contract. Whether the award will proceed without further cost changes has not been determined.

The players

PKG Contracting, Inc.

A Fargo, North Dakota contractor that submitted the lowest bid for the first phase of the Sioux City wastewater plant rebuild.

Kiewit Infrastructure Co.

A construction firm the council selected in 2025 as construction manager at risk before terminating that contract on Aug. 3.

Iowa Department of Natural Resources

The state agency that sued Sioux City in 2022 over alleged repeated environmental violations and sets the sizing requirements for the plant.

The details

Hazen and Sawyer, P.C. recommended awarding the base bid to PKG and rejecting all bid alternates, which negated an irregularity in PKG's Alternate Bid Item No. 1 concerning whether the amount was additive or deductive. The council previously selected Kiewit as construction manager at risk, a method chosen over design-bid-build, before voting unanimously to end that contract and paying Kiewit $3.2 million for preconstruction services.

Timeline

  1. 2022: Iowa DNR files suit over alleged environmental violations at the plant.

  2. 2023: Council approves a sewer rate hike to help fund the phased rebuild.

  3. 2025: Council selects Kiewit as construction manager at risk for the first phase.

  4. Aug. 3, 2025: Council unanimously terminates its contract with Kiewit.

  5. Monday: Council is asked to award the $292.3 million contract to PKG.

Political Context

The city abandoned its 2025 construction manager at risk arrangement with Kiewit after rejecting a $467 million guaranteed maximum price, choosing instead to pursue competitive bidding. The council's shift reflects the cost pressures that followed its earlier decision to raise sewer rates to fund the rebuild.

Sewer ratepayers in Sioux City are already paying higher rates to fund the plant rebuild, and the cost of this contract will shape whether those rates remain stable. Residents will see the effects of the project's progress on wastewater service through the next several years.

The takeaway

The council's vote on PKG's bid will determine whether the wastewater plant rebuild moves forward on the lower-cost path the city has now chosen. Residents should watch the outcome for any change to sewer rates or the project timeline.

What happens next

The council is scheduled to consider the PKG award on Monday, and the project must be completed by Dec. 31, 2031.

Further reading

For more on local government decisions, browse City Hall coverage.

Source note: This article includes information reported by Sioux City Journal.