Davenport Reopens Eastern Avenue Bridge Over Duck Creek

The reconstructed bridge, raised three feet, reopened to traffic after a months-long closure near MercyOne Genesis East.

Updated on Nov. 25, 2026 in Business

Photograph of a newly raised concrete and steel bridge spanning a calm creek, with a riverside trail and spring trees along the banks.
Davenport reopened the Eastern Avenue bridge over Duck Creek to traffic Monday at 1:15 p.m., after a months-long reconstruction that closed the route near MercyOne Genesis East. AI Illustration. Upload story photo >

Live Poll

Do you trust your local government to spend infrastructure money wisely?

Davenport reopened the Eastern Avenue bridge over Duck Creek to traffic at 1:15 p.m. Monday, after reconstruction that closed Eastern Avenue between 29th and 31st Streets since spring 2026. The city is also reconstructing the pond at Eastern Avenue Park.

Why it matters

Eastern Avenue is a primary route to the MercyOne Genesis East hospital campus, so the reopening restores a key connection for drivers in Davenport. The raised structure is designed to help keep flash flooding on Duck Creek from affecting the bridge.

The bridge project cost just over $3 million, funded by $2 million in federal grants and $1 million in city matching funds. The reconstructed bridge sits three feet higher than the structure it replaced, and the timeline for completing the adjacent pond work has not been announced.

The players

Jim Schroeder Construction Inc.

A Bellevue, Iowa-based construction firm that performed the Eastern Avenue bridge reconstruction over Duck Creek.

MercyOne Genesis East

A hospital campus in Davenport, Iowa, that Eastern Avenue serves as a primary route to.

The details

The bridge was reconstructed by Jim Schroeder Construction Inc. of Bellevue, Iowa, and the Duck Creek Trail now passes underneath the new span rather than crossing Eastern Avenue at a traffic light. Trail users previously had to cross at that signal.

Timeline

  1. Spring 2026: Bridge reconstruction began and Eastern Avenue closed between 29th and 31st Streets.

  2. Monday, November 2026: Eastern Avenue reopened at 1:15 p.m.

Roadmap

The project raises the bridge elevation to reduce flood exposure on Duck Creek, a approach used by Iowa municipalities facing repeated flash flooding on local waterways. It also pairs the crossing with a trail routed underneath, separating pedestrian and bicycle traffic from Eastern Avenue vehicles.

Drivers using Eastern Avenue between 29th and 31st Streets can once again cross Duck Creek without the closure that had lasted since spring 2026. Trail users no longer need to stop at a traffic light to cross Eastern Avenue, since the Duck Creek Trail now runs underneath the bridge.

The takeaway

Raising the bridge and routing the trail beneath it shows how a single crossing can address both flood risk and pedestrian safety. Residents who regularly use Eastern Avenue or the Duck Creek Trail now have a more continuous route.

Further reading

Explore more Construction coverage on Davenport infrastructure projects.