The City of Ames will commence a $23.6 million reconstruction project at the Ames Municipal Airport in 2027. This initiative will see the complete rebuilding of the 5,701-foot Runway 01/19 and improvements to Runway 13/31.
Why it matters
The project is required to reconstruct the runway, which was originally constructed in 1986 and last underwent major rehabilitation in 2004. Upgrades include enhanced drainage, lighting, and navigational aids to ensure ongoing airport utility.
The project covers the reconstruction of the entire 5,701-foot Runway 01/19. Funding includes a $7.8 million initial FAA grant with a projected $12.7 million second grant expected in spring 2027.
The players
City of Ames
The local municipal government that owns the airport and oversees public infrastructure projects.
James Herman Banning
The airfield was renamed in his honor in June 2023 to recognize his status as a pioneer in American aviation.
Central Iowa Air Service
The company that has leased and operated the municipal airport facilities since 2017.
The details
The work encompasses critical upgrades to grading, signage, pavement markings, and drainage systems for both runways. The airport, now named for James Herman Banning, has been under a 2017 lease agreement with Central Iowa Air Service.
Timeline
1943: Ames citizens voted to establish a municipal airport.
1986: Runway 01/19 was originally constructed.
2004: Runway 01/19 received a major rehabilitation.
Spring 2027: Construction is expected to begin.
July 2027 - September 2027: Both airport runways will be closed.
Travel Outlook
This reconstruction project fits into the broader cycle of national airport infrastructure maintenance funded by the Federal Aviation Administration's Airport Improvement Program. It reflects the ongoing effort to replace legacy pavement surfaces that have exceeded their standard design lifespan.
Travelers and local pilots should prepare for complete airport closures during the peak construction window from July to September 2027. All flight operations will be suspended during these months to accommodate the required safety and paving work.
The takeaway
Maintaining aging infrastructure is a cyclical necessity for municipal airports to ensure safety and compliance with modern standards. Residents and airport users should plan for significant operational disruptions throughout the summer of 2027.
What happens next
Major construction is scheduled to start in spring 2027, followed by a full closure of both runways from July through September 2027.
Further reading
For more information on regional transit updates, visit the Air Travel section.
Source note: This article includes information reported by USA TODAY.
Live Poll
Do you support the planned multi-month closure of your local airport for a runway reconstruction project?