Hawaii's Public Utilities Commission ordered that liquefied natural gas proposals for Oahu go through competitive bidding, and set a framework for the next stage of Hawaiian Electric's Integrated Grid Plan. The order came as JERA Americas pursued a $2 billion, 500-megawatt LNG-fueled plant outside that bidding process.

Why it matters

The order will shape how Hawaii plans its energy supply over the next three years, and any fossil-fuel proposal must reconcile with the state's 2045 clean energy goal and the non-displacement of renewables. The decision affects whether large gas infrastructure is weighed against renewable and storage options on equal terms.

The Public Utilities Commission denied Hawaiian Electric's request for expedited approval of up to 500 megawatts of additional fuel-flexible firm generation on Oahu. The order does not resolve whether JERA's plant will proceed, and the Governor's Office said it is reviewing the decision.

The players

Hawaii Public Utilities Commission

The state regulator that issued the order requiring competitive bidding for LNG proposals and set guidelines for Hawaiian Electric's grid planning.

Hawaiian Electric

Hawaii's largest electric utility, which is developing its Integrated Grid Plan and filed the request for proposals on the same day as the PUC order.

JERA Americas

The U.S. arm of Japan's JERA energy company, which proposed the $2 billion LNG-fueled plant for Oahu outside the competitive bidding process.

JERA Co.

The Japanese parent company of JERA Americas, which is the home company behind the proposed Oahu LNG project.

The details

The order requires any LNG proposal to go through a competitive bidding process and sets guardrails tying fossil-fuel plans to the state's 2045 goal, price volatility and the non-displacement of renewables. JERA Americas had filed a notice of intent in July to establish GenCo, and JERA said outside-process filing was meant to allow a shorter procurement timeline. Hawaiian Electric filed its request for proposals for integrated grid planning on the same day.

Timeline

  1. July: JERA Americas filed a notice of intent to establish GenCo.

  2. March: JERA proposed the $2 billion LNG plant to state officials.

  3. Friday, November 20, 2026: The PUC order was filed and Hawaiian Electric filed its request for proposals.

  4. 2030: JERA's target for bringing LNG online.

  5. 2045: The state's net-zero carbon goal deadline.

Market Landscape

The order places the LNG plant within Hawaii's 2045 net-zero carbon goal, requiring fossil-fuel proposals to be measured against that deadline. It sets up a contest between gas infrastructure and renewable and storage projects on Oahu's grid.

The outcome will influence how much Hawaii residents pay for electricity and which generation sources are built on Oahu over the next several years. Any LNG plant that wins approval would need to be reconciled with price volatility and renewable goals before it can proceed.

The takeaway

Residents and businesses should watch how the bidding process treats gas plants alongside solar, wind and storage, since that comparison will shape future power costs on Oahu. The 2045 goal is the benchmark the state will use to judge every proposal.

Further reading

For more on how the state is planning its power supply, see Utilities coverage across Hawaii.

Source note: This article includes information reported by Honolulu Star Advertiser.

Live Poll

Do you think Hawaii's electricity bills will get better or worse in your area?