Army Corps Approves Savannah Container Terminal Permit
Georgia Ports Authority will proceed with developing a 3.5 million TEU terminal on Hutchinson Island after a three-year federal review.
Updated on Nov. 27, 2026 in Transportation

Live Poll
Do you think the new port expansion will improve economic conditions in your area?
The U.S. Army Corps of Engineers approved the Savannah Container Terminal permit following a three-year review, as announced by Georgia Ports Authority President Kevin Price at the State of the Port of Savannah event on October 14. The $2.3 billion terminal on Hutchinson Island is planned to add capacity to Savannah's current 7.75 million TEU.
Why it matters
The Port of Savannah is the third-busiest container port in the United States, and the approval clears a major step toward expanding its capacity for the largest container ships. Savannah's reach is also growing inland through the new Gainesville Inland Port, which offers shorter trips than the five or six hours by truck.
The $2.3 billion Savannah Container Terminal would add 3.5 million TEU to the port's current 7.75 million TEU capacity. The $1.6 billion Ocean Terminal upgrade is expected to be completed by the end of 2028.
The players
Georgia Ports Authority
The state agency that operates the Port of Savannah and oversees its expansion projects, including the Gainesville Inland Port and the planned Hutchinson Island terminal.
U.S. Army Corps of Engineers
The federal agency responsible for permitting work in navigable waters and wetlands, which completed the three-year review of the Savannah Container Terminal.
Kevin Price
The president of the Georgia Ports Authority, who announced the permit approval at the State of the Port of Savannah event.
Griff Lynch
The longtime CEO of Georgia Ports, who is set to retire on August 1, 2027, after 16 years leading the agency.
The details
The Georgia Ports Authority hosted its annual State of the Port of Savannah event on October 14, where President Kevin Price announced the permit approval. The 350-acre terminal on Hutchinson Island is expected to handle the largest container ships, with completion projected for the mid-2030s.
Timeline
October 13: Georgia Ports named Lowe's Supply Chain Impact Partner of the Year at the Lowe's Supply Chain Summit.
October 14: State of the Port of Savannah event, where the permit approval was announced.
October 29: The $134 million Gainesville Inland Port opened.
January 2028: Construction of the Savannah Container Terminal is scheduled to start.
August 1, 2027: GPA CEO Griff Lynch is set to retire after 16 years with Georgia Ports.
Market Landscape
The approval follows the federal permit review process for major port construction and positions Savannah to compete for East Coast container volume as ships grow larger. Savannah's container volume has grown 90 percent under Griff Lynch since 2011, a trend the new terminal is designed to sustain.
Expanded container capacity at the Port of Savannah can affect the cost and availability of imported goods that move through Georgia's ports. The Gainesville Inland Port offers an alternative to the five or six hours of truck travel that Savannah-bound freight previously required.
The takeaway
The permit approval moves a multibillion-dollar expansion closer to construction, and the port's inland reach through Gainesville shows that shippers now have more options than a single coastal terminal. Readers tracking freight costs should watch the 2028 construction start and the mid-2030s completion timeline.
What happens next
Construction on the Savannah Container Terminal is scheduled to start in January 2028, and Griff Lynch retires on August 1, 2027.
Further reading
For more on regional freight infrastructure, see Transportation coverage across the Savannah area.
Source note: This article includes information reported by The Waterways Journal.