Marietta Water Begins Church Street Sewer Work
Lane closures near Wellstar Kennestone Regional Medical Center are part of a phased replacement of aging sewer mains.
Updated on Nov. 16, 2026 in Lifestyle

Marietta Water began lane closures on Church Street near Wellstar Kennestone Regional Medical Center on Monday for a sewer replacement project. Access to homes, businesses and emergency services will be maintained throughout construction.
Why it matters
The existing sewer line has reached the end of its service life and requires replacement to maintain reliable service for Marietta residents. Drivers and nearby businesses in the area should expect traffic disruptions as the work proceeds in phases.
The project replaces approximately 3,800 linear feet of sewer mains ranging from eight to 12 inches in diameter. Marietta Water has not disclosed the project cost in the available information, and the length of each phase's lane closures remains unspecified.
The players
Marietta Water
Marietta Water is the municipal water and sewer utility serving the city of Marietta, Georgia, and is responsible for maintaining the local sewer infrastructure.
The details
The project covers portions of Church, Cherokee and Cherry streets, Etowah and Chicopee drives, Allgood Road, Wellons Street and Pine Street. Marietta Water is completing the work in phases that began in May, and access to homes, businesses and emergency services is being maintained throughout.
Timeline
May 2026: Phased sewer project work began.
Monday, November 16, 2026: Church Street lane closures began near Wellstar Kennestone Regional Medical Center.
Early 2027: The full sewer project is expected to be completed.
Home Renovation Context
Sewer replacement projects like this one reflect the broader need to renew underground utility lines that have reached the end of their service life. Homeowners in the affected neighborhoods often see such municipal work as a precursor to any private landscaping or driveway improvements they plan.
Drivers using Church Street near Wellstar Kennestone Regional Medical Center should plan for lane closures and possible detours during construction. Residents and businesses along the affected streets can expect access to be maintained throughout the work.
The takeaway
Residents near the work zone should allow extra travel time through Church Street and keep an eye on Marietta Water notices as the project moves through its phases. Planning ahead can help avoid delays while the aging sewer lines are replaced.
What happens next
The full sewer project is expected to be completed in early 2027, with phased work and lane closures continuing until then.