Data Center Campus Proposed Near Augusta Airport
A local investment firm seeks rezoning for a seven-building, 383-acre data center campus in South Augusta.
Updated on Nov. 23, 2026 in Data Centers

Live Poll
Would you support a large data center built near your neighborhood?
A local investment firm is seeking rezoning and a special exception to establish a seven-building data center campus on about 383 acres near Augusta Regional Airport. The Augusta-Richmond County Planning Commission will hear the proposal Monday afternoon.
Why it matters
The Planning Commission makes a recommendation on the request, but the Augusta Commission holds final authority on zoning matters. The project's scale raises questions for Augusta residents about land use, power demand and local tax revenue.
The regional impact review form estimates a peak electrical load of 600 megawatts, with Georgia Power named as the electricity provider. Final power-supply arrangements and the grid impact of that load have not been addressed in the materials available.
The players
Augusta-Richmond County Planning Commission
The local body that reviews zoning requests and makes a recommendation to the Augusta Commission, which holds final authority.
Georgia Power
The electric utility identified in the regional impact review form as the electricity provider for the proposed campus.
The details
The proposal covers land at 1538 and 1550 Four H Club Road and 3806 Mike Padgett Highway, and a local investment firm is applying on behalf of a local landowner group. The campus would include seven buildings, with minimum setbacks of 500 feet from existing residential properties and daytime and nighttime noise caps of 65 and 60 decibels under city ordinance.
Timeline
Monday afternoon: Augusta-Richmond County Planning Commission hears the data center proposal.
The Tech Race
The 600-megawatt peak load estimated in the regional impact review form places this campus among large data center proposals that depend on dedicated power supply. The scale of the request puts it in the same class of projects that local governments are now weighing against land-use and utility concerns.
Residents near the proposed site would be affected by the campus's noise limits and setback requirements if approved. Changes to local tax revenue and job figures would depend on the final version of the project and any Augusta Commission action.
The takeaway
Large data center proposals bring major changes to land use, power demand and local tax revenue, so residents should watch how the Planning Commission and Augusta Commission handle the request. Attending or following public zoning hearings is the most direct way to track the outcome.
What happens next
The Augusta-Richmond County Planning Commission hears the proposal Monday afternoon, with a recommendation then forwarded to the Augusta Commission for final zoning authority.
Further reading
Explore more on Data Centers in the Augusta area.
Source note: This article includes information reported by Wrdw.