Augusta Commission Reviewed Data Center Ordinance
The commission addressed a discrepancy in previous voting records before moving toward final ordinance adoption.
Updated on Oct. 6, 2026 in Data Centers

Live Poll
Should your local government enact stricter zoning rules to control data center development in your community?
The Augusta Commission met to review a data center ordinance and finalize meeting minutes that incorrectly recorded a September 15 vote. Commissioners are now moving to formalize regulations governing data center location, noise levels, and water usage.
Why it matters
The ordinance is critical for establishing clear operational standards for data centers in the area, following a period of regulatory uncertainty marked by a 60-day moratorium. Finalizing these rules ensures that infrastructure projects proceed with defined community protections.
The September 15 vote to approve the ordinance passed 6-5, despite minutes incorrectly listing an 11-0 result. Previous regulatory efforts included a 60-day moratorium on new data center projects established following a July 21 meeting.
The players
Stacy Pulliam
Stacy Pulliam is an Augusta commissioner who intends to introduce amendments to the ordinance to include developer-funded utility protections.
Chastanae Cherry
Chastanae Cherry is an advocate scheduled to testify before the commission regarding the formation of a data center oversight committee.
Augusta Commission
The Augusta Commission is the governing body responsible for setting local ordinances and managing municipal infrastructure policy for the city.
The details
Commissioners evaluated the data center ordinance as the first item on the consent agenda, which outlines rules for setbacks, noise, and water use. During the proceedings, Commissioner Stacy Pulliam proposed adding utility protections funded by developers, while Chastanae Cherry presented plans for an oversight committee.
Timeline
July 21: Commissioners voted to extend a data center moratorium.
September 9: City officials released the final draft of the data center ordinance.
September 15: Commissioners originally approved the ordinance in a 6-5 vote.
October 7, 2026: The Augusta Commission convened to vote on the ordinance.
Roadmap
This ordinance represents a shift from a temporary moratorium to permanent municipal oversight of the local digital infrastructure landscape. By setting specific standards for noise and water use, Augusta is positioning itself to manage the influx of high-density computing facilities.
Residents may see changes in noise regulation and local utility management as the city implements new standards for data center developers. These rules are designed to balance the growth of local tech infrastructure with the immediate need to protect municipal water and land resources.
The takeaway
Effective data center regulation requires balancing economic growth with specific mandates for utility consumption and noise mitigation. Residents should monitor future commission meetings for finalized amendments regarding developer-funded protections.
Further reading
For additional context on the local regulatory landscape, visit Data Centers.