Naples Pier Rebuild Reaches Framing Milestone
Shoreline Foundation Inc. is rebuilding the Hurricane Ian-destroyed Naples Pier under a $26 million contract, with completion targeted for mid-2027.
Updated on Nov. 27, 2026 in Industry

Shoreline Foundation Inc. is rebuilding the Naples Pier, which Hurricane Ian destroyed on September 28, 2022, under a $26 million contract awarded by the Naples City Council. The midway pavilion framing and truss installation have been completed, and groundbreaking took place in January 2026.
Why it matters
The pier has been closed to the public since the hurricane, and the rebuild restores a major waterfront landmark after a lengthy wait for federal approvals and funding. Federal agencies held up the go-ahead before the city awarded the contract.
The $11.4 million FEMA grant approved in December 2025 covers only part of the $26 million contract, which is expected to take 14 months to complete. The extraction does not specify how the remaining funding will be secured.
The players
Shoreline Foundation Inc.
Shoreline Foundation Inc. is the contractor selected by the Naples City Council to demolish the old pier and build the replacement.
The details
The city waited three years for FEMA funding approval before the December 2025 grant. The new pavilion roof uses synthetic cedar shakes instead of the original cedar shake roofing to meet current wind requirements. The western third of the pier parking lot remains open, while the eastern two-thirds is closed. Sea turtle nesting season has ended, and no nests were found in the project area.
Timeline
September 28, 2022: Hurricane Ian destroyed the Naples Pier.
October 2024: City Council awarded the demolition and build contract to Shoreline.
December 2025: FEMA approved $11.4 million in grant funding.
January 2026: Groundbreaking for the new pier occurred.
Mid-2027: Targeted completion of the new pier.
Construction Timeline
The Naples Pier rebuild follows Hurricane Ian's September 2022 destruction, which also took out the Fort Myers Beach Pier roughly 30 miles away. The three-year wait for FEMA approval shows how federal funding timelines extended recovery for both piers.
The western third of the pier parking lot remains open to the public, while the eastern two-thirds is closed during construction. Residents and visitors planning trips to the waterfront should expect limited parking until the project is complete.
The takeaway
Residents should check parking and access restrictions before visiting the waterfront during the 14-month rebuild. The project's progress can be tracked through the public construction camera as the new pier takes shape.
What happens next
Construction of the new pier is expected to take 14 months, with completion targeted for mid-2027.
Further reading
Explore more Construction coverage on Wisevoter to see how Naples projects like this one are being built.
More information
Watch the live Naples Pier construction camera for real-time progress on the rebuild.
Source note: This article includes information reported by The News-Press.