Collier County Begins Naples Beach Renourishment Project

Crews are spreading 208,000 tons of sand to revitalize 3.5 miles of coastline along Naples Beach.

Updated on Oct. 26, 2026 in Construction

An industrial sand-delivery pipe lying on white sand by the ocean in Naples, Florida, as part of a coastal restoration project.
Collier County has launched an $8 million beach renourishment project, spreading 208,000 tons of sand along 3.5 miles of Naples coastline. AI Illustration. Upload story photo >

Live Poll

Do you support using local tax dollars to fund routine beach renourishment projects in your area?

Collier County has launched a major beach renourishment project spanning 3.5 miles from Doctors Pass to 21st Avenue South. Crews began spreading 208,000 tons of sand this week as part of an $8 million initiative to revitalize the area.

Why it matters

This project serves to restore the local coastline, protecting the beach environment through a carefully coordinated effort by the county. The work ensures that the shores are maintained for the local community and visitors alike.

The total project investment is estimated at $8 million, including a $5 million construction contract awarded to Earth Tech Enterprises Inc. and $2.4 million for sand supply from Stewart Materials.

The players

Collier County Board of County Commissioners

This is the legislative body responsible for overseeing the municipal management and infrastructure projects within the county.

Earth Tech Enterprises Inc.

This construction firm based in Fort Myers was selected through a competitive bidding process to manage the beach hauling and placement.

Stewart Materials

This company serves as the supplier for the sand utilized in the renourishment project.

The details

The work covers the shoreline from Doctors Pass to 21st Avenue South, utilizing a total of 208,000 tons of sand to improve the beach. The project scope also incorporates essential expenditures for design, permitting, site inspections, and ongoing shorebird monitoring.

Timeline

  1. Crews began spreading sand during the week of October 26, 2026.

  2. Operations will pause for the Thanksgiving break from November 26, 2026, to November 29, 2026.

  3. The project is expected to reach completion by the end of 2026.

Market Landscape

This beach renourishment project aligns with the Florida Department of Environmental Protection beach management funding guidelines for coastal restoration. Such initiatives represent a significant portion of local public works, highlighting the ongoing industry demand for specialized maritime infrastructure contractors.

Residents and visitors should be aware of active construction zones extending 3.5 miles along the coastline through the end of the year. While the project aims to improve the beach, certain areas may have limited access during the work period.

The takeaway

Maintaining coastal infrastructure requires consistent investment in sand replenishment to combat natural erosion of the shoreline. Residents can monitor county updates to ensure they are aware of any beach closures during the final weeks of construction.

What happens next

Work operations are scheduled to pause for the Thanksgiving holiday starting November 26, 2026, and will resume on November 30, 2026.

Further reading

Find more local developments in the Naples Construction section.

Source note: This article includes information reported by Dredgingtoday.