Fort Lauderdale Declares Emergency to Fix Riverwalk

City officials approved an emergency procurement to replace a collapsing seawall and repair a barricaded section of the Riverwalk along the New River.

Updated on Nov. 29, 2026 in City Hall

Isometric editorial illustration of a cracked concrete seawall sagging into eroding sand above slate blue river water, beside a newly poured section.
Fort Lauderdale city officials approved an emergency procurement exceeding $12 million to replace a collapsing seawall and repair a 510-foot section of Riverwalk along the New River. AI Illustration. Upload story photo >

Live Poll

Do you think Fort Lauderdale is maintaining its public infrastructure well?

Fort Lauderdale city officials declared an emergency procurement to replace a collapsing seawall and repair a 510-foot section of Riverwalk on the north side of the New River. The barricaded section is sinking into the river as soil supporting its brick pavers washes away.

Why it matters

The project, costing more than $12 million, affects public access to a key waterfront walkway in Fort Lauderdale and shows how aging infrastructure and extreme tides can accelerate damage. Officials cited king tides and heavy rainfall as factors worsening the seawall's condition.

The city's Oct. 27 public works memo requested an emergency procurement for a project costing more than $12 million over 14 to 18 months, covering a 510-foot seawall section that will be raised to 5 feet. The Nov. 13 memo cited king tides and rainfall as worsening conditions, but the source does not confirm whether the timeline or cost will change as work proceeds.

The players

Brad Kaine

Brad Kaine is the Public Works Director for the City of Fort Lauderdale, responsible for city infrastructure projects including the Riverwalk seawall.

Chris Cooper

Chris Cooper serves as Acting City Manager of Fort Lauderdale, overseeing city administration and signing off on emergency procurement requests.

The details

Soil supporting the Riverwalk brick pavers behind the seawall was lost in August, causing sections to collapse, and the city is now replacing the seawall and building a new one alongside it at 5 feet high. Acting City Manager Chris Cooper signed off on the emergency request after Public Works Director Brad Kaine submitted it.

Timeline

  1. Summer 2027: Original scheduled start of seawall construction.

  2. August 2026: Substantial soil loss behind the seawall caused Riverwalk pavers to collapse.

  3. Oct. 27, 2026: Public Works Director Brad Kaine requested the emergency procurement declaration.

  4. Nov. 13, 2026: Memo cited king tides and rainfall as worsening the seawall's condition.

  5. Mid-December 2026: Site work is expected to get underway.

Project Timeline

The emergency procurement shortens a project that began with a 2023 contractor hire and an April 2024 design start, moving the originally planned summer 2027 construction date forward to mid-December 2026.

The barricaded 510-foot Riverwalk section remains closed to pedestrians while the seawall is rebuilt, affecting walkers and waterfront users along the New River. Residents should expect construction activity and detours near the South Andrews Avenue Bridge during the 14 to 18 month project.

The takeaway

Aging waterfront infrastructure can fail quickly when soil erosion and extreme tides combine, so city repairs often cost more and take longer than originally planned. Residents who use the Riverwalk should watch for construction notices as work begins.

What happens next

Site work on the Riverwalk seawall is expected to begin by mid-December, with the overall project timeline running 14 to 18 months.

Further reading

Explore more reporting in City Hall coverage for context on local government decisions.

Source note: This article includes information reported by WPEC.