Ecoasis Plans 272-Acre Greenhouse Campus
The Pueblo, Colorado project would pair greenhouses with a compact data center that supplies waste heat to the growing operation.
Updated on Nov. 20, 2026 in Data Centers

Live Poll
Would a large new greenhouse campus in your area make local produce better for you?
Ecoasis AgTech Park has unveiled plans for a 272-acre greenhouse campus south of Pueblo, Colorado, including about 160 acres of greenhouses. The campus would also host a compact data center, capped at about 10% of the property, that would supply waste heat to warm the greenhouses.
Why it matters
Heating is a significant greenhouse cost, usually met by burning natural gas, so using data center waste heat could change how the operation is powered. The plan also projects around 1,000 permanent jobs at full build-out for the Pueblo area.
The data center would be cooled through a sealed, closed loop, and growers would recirculate irrigation water across the campus. The unit development application is still underway, so the final cooling and water specifications remain subject to county review.
The players
Ecoasis AgTech Park
Ecoasis AgTech Park is the developer behind the planned 272-acre greenhouse campus south of Pueblo, Colorado.
Thomas Larssen
Thomas Larssen is a greenhouse designer and builder with forty years of experience who co-acquired the land for the project.
Gill van der Drift
Gill van der Drift is the founder of Mountain High, a Colorado company, and co-acquired the land for the campus.
The details
Ecoasis plans to build the campus at Interstate 25 and Greenhorn Drive, on land that Thomas Larssen and Gill van der Drift acquired about 25 years ago. Larssen, who has spent forty years designing and building greenhouses, and van der Drift, founder of Mountain High, are behind the project, which would be built in phases over about four years.
Timeline
November 16, 2026: Community information session held in Pueblo.
Spring 2027: Construction planned to start.
First half of 2028: First operations projected.
About four years: Full campus built in phases.
Tech Race
The plan pairs a compact data center with greenhouse heating, extending the practice of recovering data center waste heat into controlled-environment agriculture. It positions the Pueblo project within a growing effort to reduce the natural gas burned to heat greenhouses.
Pueblo residents may see new employment opportunities if the projected 1,000 permanent jobs materialize at full build-out. The campus's greenhouse output and water-use claims would reach local consumers only after construction and operations begin, which is projected for 2027 and 2028.
The takeaway
Recovering waste heat from a data center could lower the natural gas costs of growing produce in cold months, a link worth watching as the Pueblo project moves through county review.
What happens next
Construction is planned to start in Spring 2027, and first operations are projected for the first half of 2028, pending the county's planned unit development review.
Further reading
Explore more on Data Centers to see how waste heat from computing is being reused across industries.
Source note: This article includes information reported by Horti Daily.