Fort Collins Joins Northern Integrated Supply Project
The city and Johnstown entered interim agreements as eleven water providers now take part in the regional water plan.
Updated on Nov. 24, 2026 in Business

Live Poll
Do you support your city spending on major new water storage projects?
The city of Fort Collins and the town of Johnstown have entered into interim agreements to participate in the Northern Integrated Supply Project. Eleven water providers are now participating after six others withdrew in recent months.
Why it matters
Fort Collins Utilities evaluated whether the project could store its senior water rights more affordably than the Halligan Reservoir expansion, which began facing permitting challenges. The shift affects how Fort Collins secures future water supply for residents.
The project proposes up to 40,000 acre-feet of new water supply, and 11 providers now participate after six withdrew in recent months. Participants' final costs and the project's long-term funding were not addressed in the source material.
The players
Fort Collins City Council
The elected governing body of Fort Collins, Colorado, which voted to withdraw the Halligan permit applications and approve participation in the project.
Northern Water
A Colorado water conservancy district that sponsors and manages the Northern Integrated Supply Project and its proposed Glade Reservoir.
Fort Collins Utilities
The municipal utility department of Fort Collins that evaluated the project as a storage option for the city's senior water rights.
The details
Under an annually updated interim agreement, Northern Water and project participants can advance work on the project. The U.S. Army Corps of Engineers states the Halligan project is no longer the least environmentally damaging practicable alternative because Glade Reservoir would have enough room after participant withdrawals. In 2024, the Fort Collins City Council rescinded all prior resolutions opposing the project, and on November 3 it gave final approval to pursue participation.
Timeline
October 20, 2026: City Council voted to withdraw Halligan permit applications filed with the U.S. Army Corps of Engineers.
November 3, 2026: City Council gave final approval to pursue participation in the project.
November 30, 2026: First Fort Collins Utilities information session.
December 17, 2026: Second Fort Collins Utilities information session.
Early 2027: Northern Water Board selects contractors.
Market Landscape
Fort Collins is shifting from its Halligan Reservoir expansion, whose federal permit applications it withdrew in October, toward a regional supply project. The move reflects how Front Range water providers are consolidating storage plans across shared reservoirs rather than building separate single-city projects.
Fort Collins residents may see long-term water supply decisions shaped by this regional project rather than the Halligan expansion. Households would not see immediate changes, as construction of large-scale project elements is not expected to begin until 2028.
The takeaway
Residents interested in how their water is planned can attend the upcoming Fort Collins Utilities information sessions. Following the project's contractor selection in early 2027 will show how participant costs take shape.
What happens next
Fort Collins Utilities will host information sessions on November 30 and December 17, 2026, and the Northern Water Board is expected to select contractors in early 2027.
Further reading
For broader context on how local providers plan future supply, explore more Utilities coverage on Wisevoter.
Source note: This article includes information reported by The Coloradoan.
Live Poll
Do you support your city spending on major new water storage projects?