The Denver Auditor's Office released an audit finding little accountability in the $1.6 billion National Western Center redevelopment. The city and the National Western Center Authority agreed to implement 27 of the audit's 28 recommendations.

Why it matters

The audit points to missing measurable goals and incomplete event, attendance and tax records for a project that has committed more than $1 billion in public and private funding. Its findings bear directly on how Denver residents' tourism tax dollars are tracked and spent.

The Denver Auditor's Office has published its findings, and the city and National Western Center Authority have agreed to implement 27 of 28 recommendations. Whether the declined invoice-review and procedure policies will later be adopted remains unaddressed.

The players

Denver Auditor's Office

The independent office responsible for auditing Denver city government operations and spending.

National Western Center Authority

The entity created to operate and manage the National Western Center campus in Denver.

City of Denver

The municipal government that co-manages the National Western Center redevelopment with the authority.

The details

Auditors reviewed invoices, procedures and processes for oversight, expense documentation and finances. The report found the authority's visitor "round up" fundraising leaves visitors unclear whether amounts are tips or donations, and that the city's relationship with the Globeville and Elyria-Swansea neighborhoods is deteriorating.

Timeline

  1. 2015: Ballot Measure 2C approved $778 million in tourism tax funding for National Western Center and Colorado Convention Center improvements.

  2. Last year: Denver City Council approved $800 million in additional tourism tax funding.

  3. November 25, 2026: The Denver Auditor's Office published its report on the National Western Center.

  4. In the coming years: The equestrian center is expected to be completed, along with a 160-room hotel and repurposing of a historic building.

Legal Context

The audit follows Ballot Measure 2C, approved by Denver voters in 2015, which directed $778 million in tourism tax funding to the National Western Center and Colorado Convention Center. The report now examines whether that voter-authorized spending is being overseen with the accountability the measure's scale implies.

Residents who pay Denver tourism taxes are funding a project whose spending is not yet tracked with measurable goals or reliable event and attendance records. The audit's recommendations, if fully carried out, would give the public clearer data on how that money is used.

The takeaway

Public accountability for large, multi-agency projects depends on measurable goals and complete records, and the National Western Center audit shows how their absence can leave billions in tax-funded spending hard to evaluate. Readers can watch whether the agreed recommendations are carried out.

What happens next

The city and authority have agreed to implement 27 of the 28 audit recommendations, and the remaining recommendation and the planned development of the 50-acre "Triangle" area are still pending.

Further reading

Follow more local accountability coverage in Denver City Hall.

Source note: This article includes information reported by Denverite.

Live Poll

Do you trust your local government to spend public money responsibly?