Denver Construction Impacted Local Businesses

The $29 million Santa Fe Streetscapes Project has led to sales declines for area restaurants.

Updated on Oct. 11, 2026 in Openings & Closings

Denver Construction Impacted Local Businesses

Live Poll

Should city governments provide financial aid to small businesses harmed by ongoing local construction projects?

Since Denver Water began work on August 10, 2026, the ongoing Santa Fe Streetscapes Project has disrupted local business operations. Restaurant owners reported a 30% drop in sales as crews continue to replace 136-year-old water mains.

Why it matters

City officials launched the initiative to improve safety and accessibility for the corridor. However, the lengthy construction timeline has created significant challenges for business owners along the route.

The $29 million project includes the replacement of 2,800 feet of water mains. A local restaurant owner reports a 30% drop in sales since the work began in August.

The players

Denver Water

This public agency provides water services to the city and is responsible for replacing the 136-year-old water mains.

Xcel Energy

This utility provider operates in the region and is scheduled to begin gas main replacement work in October.

The details

The project involves reconstructing the roadway between West 6th and West 13th Avenues to improve infrastructure. While crews maintain at least one lane of traffic, drivers are directed to use East 6th Avenue and northbound Speer Boulevard to avoid delays.

Timeline

  1. August 10, 2026: Denver Water began replacing aging water mains.

  2. October 12, 2026: Xcel Energy begins replacing a gas main.

  3. Late October 2026: Roadway and stormwater improvements begin.

  4. End of 2026: Utility improvements are expected to be complete.

  5. End of 2028: Full project is scheduled for completion.

Market Landscape

The Santa Fe Streetscapes Project is funded by the Vibrant Denver Bond Program, which aligns with the city's broader infrastructure investment strategy. This project follows a pattern of urban revitalization funding established by the bond program to modernize aging city utilities.

Local shoppers may face traffic detours and limited street access near Santa Fe Drive until 2028. Business owners are currently navigating the financial strain caused by ongoing construction-related foot traffic disruptions.

The takeaway

Ongoing infrastructure projects often create short-term volatility for small businesses reliant on consistent street access. Residents should plan for long-term construction delays in the area through 2028.

What happens next

Utility improvements are expected to be finished by the end of 2026, while the full streetscape project is scheduled for completion by the end of 2028.

Further reading

For more updates on local commercial developments, visit the Denver Openings & Closings.

Source note: This article includes information reported by CBS News.